From the main Scheduling Environment Selection List panel, put the cursor under the Resources field at the top of the screen and press Enter. When the pop-up box appears, enter a 1, as shown in Figure 1. (In this pop-up, 1 is the only option.)
Scheduling-Environments Notes Options Resources Help
---------------------------------------- *************************** ---
Scheduling Environment * 1 1. Process Resources * to 3 of 3
Command ===> ___________________________ *************************** ___
Action Codes: 1=Create, 2=Copy, 3=Modify, 4=Browse, 5=Print, 6=Delete,
/=Menu Bar
Action Scheduling Environment Name Description
__ CICS_SPEC Special CICS Processing
__ DB2LATE Offshift DB2 Processing
__ IMSPRIME Prime IMS Processing
This will take you directly to the Resource Definition List panel, where you can add new resources. Enter an A on any Action line, as shown in Figure 2. (Alternately, you can put a / next to the resource names and then put the cursor under the Resources field at the top of the screen and hit ENTER. Then select 1 from the options in the pop-up box.)
Resources Notes Options XREF Help
------------------------------------------------------------------------
IWMAPAR Resource Definition List Row 1 to 4 of 4
Command ===> ___________________________________________________________
Action Codes: A=Add D=Delete X=XREF /=Menu Bar
Action Resource Name In Use Resource Description
__ CICS001 YES CICS Subsystem
__ DB2A YES DB2 Subsystem
__ IMS1 YES IMS Subsystem
a_ PRIMETIME YES Peak Business Hours
This would take you to the Define Resource panel, where you would enter the information for the new resource name, as shown in Figure 3.
IWMAPAE Define Resource
Command ===> ___________________________________________________________
Resource name . . . . . . . . VECTOR__________ Required
Resource Description . . . . . Vector Processor________________
When we return to the Resource Definition List panel, the new resource name is there, as shown in Figure 4.
Resources Notes Options XREF Help
------------------------------------------------------------------------
IWMAPAR Resource Definition List Row 1 to 5 of 5
Command ===> ___________________________________________________________
Action Codes: A=Add D=Delete X=XREF /=Menu Bar
Action Resource Name In Use Resource Description
__ CICS001 YES CICS Subsystem
__ DB2A YES DB2 Subsystem
__ IMS1 YES IMS Subsystem
__ PRIMETIME YES Peak Business Hours
__ VECTOR Vector Processor
Note that the panel automatically alphabetizes the resource names. Note also that VECTOR is not yet shown as In Use. We would need to go create or modify a scheduling environment and then select VECTOR.