How do you use IS_COMPLETED statechart macro in IBM Rhapsody?
Cause
You have included the macro in your code but observe a compiler error saying the object/method is not in scope.
Answer
The IS_COMPLETED macro calls the is_completed()
state operation:
which is generated within your project's statechart.
However, the is_completed()
state operation is only generated if:
a) The state contains a final state
b) The CG::Class:IsCompletedForAllStates property is enabled. In which case the final state is not required.
See examples for both below:
[{"Product":{"code":"SSB2MU","label":"IBM Engineering Systems Design Rhapsody"},"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Component":"General Information","Platform":[{"code":"PF016","label":"Linux"},{"code":"PF033","label":"Windows"}],"Version":"8.3","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]
Product Synonym
Rational Rhapsody
Was this topic helpful?
Document Information
Modified date:
27 May 2022
UID
swg22014839