IT44335: Migration of IBM MQ Appliance HA queue manager from MQ 9.2 to 9.3 fails if the queue manager has been manually stopped

Subscribe to this APAR

By subscribing, you receive periodic emails alerting you to the status of the APAR, along with a link to the fix after it becomes available. You can track this item individually or track all items by product.

Notify me when this APAR changes.

Notify me when an APAR for this component changes.

 

APAR status

  • Closed as program error.

Error description

  • Migration of IBM MQ Appliance HA queue manager from MQ 9.2 to
    9.3 fails if the queue manager has been manually stopped before.
    High availability queue managers are reported as 'already
    migrated' when running 'sethagrp - u {QMGR}' but no HA queue
    managers could be started on the upgraded appliance.
    

Local fix

  • When updating an appliance ensure all HA queue managers are
    running on the target appliance's HA partner appliance
    

Problem summary

  • ****************************************************************
    USERS AFFECTED:
    All IBM MQ M2002 Appliance users who upgrade the firmware from
    9.2 to 9.3.
    
    
    Platforms affected:
    MultiPlatform
    
    ****************************************************************
    PROBLEM DESCRIPTION:
    Migration of queue managers with a High Availability (HA)
    configuration failed when a queue manager was manually stopped
    before the firmware upgrade to 9.3 from 9.2.
    When a HA queue manager is stopped before upgrading, an internal
    attribute which manages the state of resource is set to false,
    which affects the order constraints (rules) that the appliance
    follows to start an HA queue manager's resources. This caused
    the migration process to fail, and therefore the HA components
    initialization, as it did not update an internal metadata file.
    With no metadata file available, HA resources appeared as
    unavailable.
    

Problem conclusion

  • MQ migration process has been modified to check if the high
    availability queue manager was stopped manually prior to
    starting the queue manager's HA resources.
    
    ---------------------------------------------------------------
    The fix is targeted for delivery in the following PTFs:
    
    Version    Maintenance Level
    v9.3 LTS   9.3.0.10
    v9.x CD    9.3.4
    
    The latest available maintenance can be obtained from
    'WebSphere MQ Recommended Fixes'
    http://www-1.ibm.com/support/docview.wss?rs=171&uid=swg27006037
    
    If the maintenance level is not yet available information on
    its planned availability can be found in 'WebSphere MQ
    Planned Maintenance Release Dates'
    http://www-1.ibm.com/support/docview.wss?rs=171&uid=swg27006309
    ---------------------------------------------------------------
    

Temporary fix

Comments

APAR Information

  • APAR number

    IT44335

  • Reported component name

    MQ APPLIANCE M2

  • Reported component ID

    5900ALJ00

  • Reported release

    930

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2023-08-08

  • Closed date

    2023-08-24

  • Last modified date

    2023-09-15

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

  • Fixed component name

    MQ APPLIANCE M2

  • Fixed component ID

    5900ALJ00

Applicable component levels

[{"Business Unit":{"code":"BU053","label":"Cloud \u0026 Data Platform"},"Product":{"code":"SS5K6E","label":"IBM MQ Appliance"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"9.3","Line of Business":{"code":"LOB36","label":"IBM Automation"}}]

Document Information

Modified date:
15 September 2023