IJ34956: GRV CALENDAR IN THE GRAPHICAL VIEW TAB INCLUDES NON-WORKING TIME FROM OTHER CALENDARS

Subscribe to this APAR

By subscribing, you receive periodic emails alerting you to the status of the APAR, along with a link to the fix after it becomes available. You can track this item individually or track all items by product.

Notify me when this APAR changes.

Notify me when an APAR for this component changes.

 

APAR status

  • Closed as program error.

Error description

  • STEPS TO REPRODUCE:
    - Go to Graphical Resource View application.
    - Open record NAB-GRV. It uses Calendar = CAL.
    - Go to Graphical View tab. The various shifts are colour-coded
    in the graphical calendar.
    - Navigate to November: all working week days are highlighted
    with a green D (Day shift).
    - Go to Calendars application.
    - Create record CAL-21 (Day calendar for 2021).
    - Enter Org= EAGLENA, Start = 1Jan 2021 and End = 31DEC 2021
    and save.
    - Select Define/Apply Shifts action and select Shift DAY and
    click 'Apply Shift' (to Entire Calendar).
    - The shifts are now showing in the calendar.
    - Go to Define/Apply Non-working Time, select Thanksgiving
    (25-26 Nov) and Christmas (24 Dec), then Apply and OK.
    - Go to Graphical Resource View application.
    - Open the same record NAB-GRV.
    - Go to Graphical View tab. The various shifts are colour-coded
    in the graphical calendar.
    - Navigate to November: all working week days are highlighted
    with a green D (Day shift) except for 25-26 November: no shifts
    show for 25-26 November
    - The Non-working Time was applied to the CAL-21 calendar, NOT
    the CAL calendar. So the data in the NAB-GRV Resource List
    should not be affected because it does NOT use the CAL-21
    calendar.
    
    RESULTS:
    If you set some Non-Working Time such as public holidays to a
    given Calendar, this non-work time will be showing in Graphical
    Resource View in the calendar on the Graphical View tab, even
    when the Resource List is referencing another calendar.
    Furthermore, the Full Week option cannot be used in this case.
    EXPECTED RESULTS:
    The GRV calendar in Graphical View tab should only include
    Non-Working Time from the Calendar referenced in this GRV
    record.
    
    REPORTED IN VERSION:
    Maximo TPAE 7.6.1.2 with Scheduler 7.6.8.0
    

Local fix

  • N/A
    

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * Scheduler users                                              *
    ****************************************************************
    

Problem conclusion

  • The fix for this APAR is contained in the following maintenance
    package: release\fix pack for Release 7.6.1.3 Product
    

Temporary fix

Comments

APAR Information

  • APAR number

    IJ34956

  • Reported component name

    MAXIMO SCHEDULE

  • Reported component ID

    5724R46SE

  • Reported release

    768

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2021-09-13

  • Closed date

    2022-05-10

  • Last modified date

    2022-05-10

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

  • Fixed component name

    MAXIMO SCHEDULE

  • Fixed component ID

    5724R46SE