Error description
PROBLEM: Labor Availability is not adjusting as per the time zone in Graphical Assignment PERFORMANCE ISSUE: N STEPS TO REPRODUCE: SETUP info: Server is in Toronto, Canada Scheduler user and Work list in same time zone(Aus/Sydney) Labors/Crafts assigned same time zone(Aus/Sydney) Assigner/Scheduler is also mapped to same time zone(Aus/Sydney). STEPS: 1. Login as a user who belongs too the Australia/Sydney timezone (i.e. (GMT +10 DST/Y) Eastern Standard Time (New South Wales)) e.g. wilson / wilson 2. Bring up an existing Calendar in the Calendar application e.g.'DAY' calendar 3. Apply a shift to the calendar e.g. 'DAY' shift that starts from 7AM and finish by 3PM 4. Go to the Crafts application 5. bring up a craft e.g. 'CARP' for Carpenter craft 6. go to the "Associated Labor" tab 7. Hyperlink to the labor application, assign 'DAY' shift, 'DAY' calendar , assign the same time zone(Australia/Sydney) e.g. labor FINLEY and GATES 8. Create a new work order in Work Order Tracking application e.g. work order 'MAY5' with a description 'test5' 9. enter a target start e.g. tomorrow at 7AM 10. enter a duration e.g. 5 hours 11. go to the Plans tab, Labor sub-tab 12. click "select craft" button 13. enter 'CARP' in the Craft field 14. enter 'FIRSTCLASS' as the skill level 15. regular hours is 5 hours 16. save the record 17. Create a new work List in the Graphical Assignment application e.g. MAY 18. enter a start date e.g. 1/19/18 4:00 PM and enter a finish date e.g. 2/2/18 4:00 PM 19. enter the same calendar and shift e.g. 'DAY' calendar and 'DAY' shift 20. add a work query e.g. wonum like 'MAY%' 21. Save 22. Go to the "Assignment View" tab 23. Click the "Zoom to work" icon on the toolbar 24. Work order shows as an Orange time bar 25. Drag and drop the time bar down (i.e. assign the task to one of the labor that works the DAY' shift) 26. work order 'MAY5' with description 'TEST5' shows as a yellow time bar in the Gantt Chart NOTE: work order (yellow time bar) shows in the white region (not the grey region) 27. Drag the work order bar to a white region (i.e. reschedule the task to a labor's available section), the task still remain yellow in color indicating the labor is not available CURRENT ERRONEOUS RESULT: the time bar shows yellow indicating that the labor is not available for work even though the task has been dragged to the white section EXPECTED RESULT: the time bar should be green for the labor's available section (white section) ADDITIONAL INFO: N/A ENVIRONMENT (SYSTEM INFO): TPAE 7.6.0.8 IFIX 5 (IFIX dated 20171018) Scheduler 7.6.5 MIF 7.6.0.8 LOCAL FIX: N/A SECURITY IMPACT (Y/N): N
Local fix
N/A
Problem summary
**************************************************************** * USERS AFFECTED: * * Users of the Graphical Assignment application in Scheduler * * 7.6.5 * **************************************************************** * PROBLEM DESCRIPTION: * * LABOR AVAILABILITY IS NOT ADJUSTING AS PER THE TIME ZONE IN * * GRAPHICAL ASSIGNMENT * **************************************************************** * RECOMMENDATION: * ****************************************************************
Problem conclusion
A code fix has been delivered to the stream.
Temporary fix
Comments
APAR Information
APAR number
IJ03643
Reported component name
MAXIMO SCHEDULE
Reported component ID
5724R46SE
Reported release
765
Status
CLOSED PER
PE
NoPE
HIPER
NoHIPER
Special Attention
NoSpecatt / Xsystem
Submitted date
2018-01-25
Closed date
2018-01-29
Last modified date
2018-01-29
APAR is sysrouted FROM one or more of the following:
APAR is sysrouted TO one or more of the following:
Modules/Macros
MAXIMO
Fix information
Fixed component name
MAXIMO SCHEDULE
Fixed component ID
5724R46SE
Applicable component levels
R765 PSY
UP
[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SS9NUN","label":"Maximo Asset Management Scheduler"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"765","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]