APAR status
Closed as program error.
Error description
PROBLEM: Incorrect duration of child work orders after running CPM STEPS TO REPRODUCE: 1) Create a Work Order (estimated duration value 95.0 hours) Enter a Scheduled Start Date e.g. 11/07/19 12:35 AM Enter a Scheduled Finish (end date) e.g. 11/09/19 12:34 AM i.e. work order spans over 2 months Enter a duration of 95:00 hours 2) Go to the Plans tab Click New Row button Expand the child work order NOTE: Scheduled start and finish dates have been copied from the parent Enter 9:30 hours as the estimated duration Click New Row button and enter 9:30 hours as the estimated duration Save the record i.e. Each child work order's estimated duration do NOT align with the children work orders' schedule dates 3) Create a new schedule in Graphical Scheduling application Enter a schedule name Enter calendar and shift information Enter start and enter dates to cover a 2 month period e.g. from 11 July - 11 Sept 4) Go to "Graphical View" and select the 2 child work orders 5) Click "Create Constraints" icon on the toolbar 6) Click "Zoom to Work " icon on the toolbar 7) Select the parent work order and select the "Critical Path Method on ALL rows" icon RESULTS: After CPM is run, Gantt Chart shows that each child wo takes 2 months to complete. Each child should take 9:30 hours to complete EXPECTED RESULTS: After CPM is run, it should show the correct duration of the child work orders REPORTED IN VERSION: IBM Maximo Asset Management Scheduler 7.6.7.1
Local fix
Problem summary
**************************************************************** * USERS AFFECTED: * * Users of the Graphical Scheduling application in Maximo * * 7.6.1. * **************************************************************** * PROBLEM DESCRIPTION: * * INCORRECT DURATION OF CHILD WORK ORDERS AFTER RUNNING CPM * **************************************************************** * RECOMMENDATION: * ****************************************************************
Problem conclusion
A code fix has been made to address this problem.
Temporary fix
Comments
APAR Information
APAR number
IJ17561
Reported component name
MAXIMO ASST MGM
Reported component ID
5724R46AM
Reported release
761
Status
CLOSED PER
PE
NoPE
HIPER
NoHIPER
Special Attention
NoSpecatt / Xsystem
Submitted date
2019-07-11
Closed date
2019-08-01
Last modified date
2019-08-01
APAR is sysrouted FROM one or more of the following:
APAR is sysrouted TO one or more of the following:
Modules/Macros
MAXIMO
Fix information
Fixed component name
MAXIMO ASST MGM
Fixed component ID
5724R46AM
Applicable component levels
[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SSLKT6","label":"IBM Maximo Asset Management"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"761","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]
Document Information
Modified date:
01 August 2019