APAR status
Closed as program error.
Error description
When a Forecast is generated in the Preventive Maintenance application and then a schedule is created in Graphical Scheduling of that pm record, any changes to the segments via a right-click action and selecting Move to Next Day the PM record line in the Activity section table (left-hand side) does not turn red STEPS TO REPRODUCE: Go to PM application and insert new record LOcation = BR200 Go to Frequency Tab, Use Last Work Order's Start Date to Calculate Next Due Date=checked, Frequency=1, Frequency Units=WEEKS, Estimated Next Due Date=today's_date Save record Change status to ACTIVE Click on Forecast tab, make sure the "Reforecast Subsequent Dates" flag is checked. More Actions<Generate Forecast In Generate Forecast dialog box, Forecast Until=date_2_weeks_at _least Click OK Go to Graphical Scheduling and create a Schedule for that PM, Calendar=DAY, Shift=DAY Under Work Queries click new row, Data Source=PM, Where Condition=pmnum like 'PM_NUM' Click on Graphical View tab, you should see at least 2 PM segments, Zoom out if appropriate Find the 1st segment. Right-click on it and select menu option Move to Next Day (or Move Day) RESULTS:Segment moves, turns orange (as expected) but the PM record line in the Activity section table (left-hand side) does NOT turn red Now using the mouse click on and drag the segment to a different date. RESULTS:Now the PM record line turns red. EXPECTED RESULTS:It should turn red upon any date change. REPORTED IN VERSION: Maximo Asset Management 7.6.0.9
Local fix
Problem summary
**************************************************************** * USERS AFFECTED: * * Users of the Graphical Scheduling application in Scheduler * * 7.6.7. * **************************************************************** * PROBLEM DESCRIPTION: * * FORECASTED PM RECORDS REPRESENTED IN GRAPHICAL SCHEDULING * * DON'T TURN RED ON MOVE * **************************************************************** * RECOMMENDATION: * ****************************************************************
Problem conclusion
A code fix has been made.
Temporary fix
Comments
APAR Information
APAR number
IJ13571
Reported component name
MAXIMO SCHEDULE
Reported component ID
5724R46SE
Reported release
767
Status
CLOSED PER
PE
NoPE
HIPER
NoHIPER
Special Attention
NoSpecatt / Xsystem
Submitted date
2019-02-18
Closed date
2019-02-23
Last modified date
2019-02-23
APAR is sysrouted FROM one or more of the following:
APAR is sysrouted TO one or more of the following:
Modules/Macros
MAXIMO
Fix information
Fixed component name
MAXIMO SCHEDULE
Fixed component ID
5724R46SE
Applicable component levels
R767 PSY
UP
[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SS9NUN","label":"Maximo Asset Management Scheduler"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"767","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]
Document Information
Modified date: