APAR status
Closed as program error.
Error description
PROBLEM: GSLP - The Critical Path highlight colors are considering the Non work time at FLOAT calculation when the records are Not Interruptible PERFORMANCE ISSUE: NO PRE CONDITIONS: - Create one Work Order with 6 tasks 2 hours each - Use a Shift of 8 hours per day - Link all tasks as predecessors STEPS TO REPRODUCE: - Go to Graphical Scheduling Large Project application - Open an existing record with the 8 hours shift and the work Order with tasks and move to Graphical View - Click at the CPM button CURRENT ERRONEOUS RESULT: The 6 tasks get align but just 2 get highlighted for the Critical PATH EXPECTED RESULT: As is working for Interruptible Work all 6 should be highlighted. Removing the Non working time from FLOAT. ADDITIONAL INFO: NO ENVIRONMENT (SYSTEM INFO): App Server IBM WebSphere Application Server 9.0.0.7 Version Tivoli's process automation engine 7.6.1.0-IFIX20181107-1300 Build 20180718-1141 DB Build V7610-83 IBM Maximo Asset Management Work Centers 7.6.0.4 Build 20180712-1824 DB Build V7604-119 IBM Maximo Calibration 7.6.0.0 Build 20180718-1141 DB Build V7600-06 IBM Maximo for Aviation 7.6.8.0 Build 20181113-2334 DB Build V7680-22 IBM Maximo Asset Management Scheduler 7.6.7.2 Build 20181114-1711 DB Build V7672-23 IBM TPAE Integration Framework 7.6.1.0 Build 20180717-1722 DB Build V7610-02 IBM Maximo Asset Management Scheduler Plus 7.6.7.1 Build 20180718-1141 DB Build V7671-01 IBM TPAE OS/REST Framework 7.6.1.0 Build 20180718-1141 DB Build V7610-38 IBM Maximo Asset Management 7.6.1.0 Build 20180718-1141 DB Build V7604-01 IoT Connection Utility 7.6.0.1 Build 20180709-1524 DB Build V7601-02 Server OS Windows Server 2012 R2 6.3 Server DB DB2/NT64 10.5 (SQL10058)
Local fix
Set the Work as Interruptible
Problem summary
**************************************************************** * USERS AFFECTED: * * Users of the Graphical Scheduling Large Projects application * * in Scheduler 7.6.7. * **************************************************************** * PROBLEM DESCRIPTION: * * THE CRITICAL PATH HIGHLIGHT COLORS ARE CONSIDERING THE NON * * WORK TIME AT FLOAT CALCULATION * **************************************************************** * RECOMMENDATION: * ****************************************************************
Problem conclusion
A code fix has been delivered.
Temporary fix
Comments
APAR Information
APAR number
IJ12477
Reported component name
MAXIMO SCHEDULE
Reported component ID
5724R46SE
Reported release
767
Status
CLOSED PER
PE
NoPE
HIPER
NoHIPER
Special Attention
NoSpecatt / Xsystem
Submitted date
2019-01-02
Closed date
2019-01-14
Last modified date
2019-01-14
APAR is sysrouted FROM one or more of the following:
APAR is sysrouted TO one or more of the following:
Modules/Macros
MAXIMO
Fix information
Fixed component name
MAXIMO SCHEDULE
Fixed component ID
5724R46SE
Applicable component levels
R767 PSY
UP
[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SS9NUN","label":"Maximo Asset Management Scheduler"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"767","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]