Fixes are available
APAR status
Closed as program error.
Error description
The performance of the "Copy item to" and "Move item to" operations in IBM Process Designer can be very slow. You might notice three REST or EJB calls between the Process Designer and IBM Process Center for each process application or toolkit track. The network latency of the individual calls can add up to a large delay. You experience this delay after you select the "Copy item to" or "Move item to" options just before you are shown the additional options, such as "Other Process App" or "Other Toolkit". PRODUCTS AFFECTED: IBM Business Process Manager (BPM) Advanced IBM BPM Standard IBM BPM Express
Local fix
Problem summary
"Copy item to" and "Move item to" operations are slow in Process Designer when there is high network latency, you have a large number of process applications or toolkits in the environment, or both situations occur.
Problem conclusion
A fix is available for IBM BPM V8.5.0.1 that optimizes the algorithm of retrieving data between Process Designer and Process Center server. On Fix Central (http://www.ibm.com/support/fixcentral), search for JR51292 (it is a replacement interim fix for JR50807): 1. Select IBM Business Process Manager with your edition from the product selector, the installed version to the fix pack level, and your platform, and then click Continue. 2. Select APAR or SPR, enter JR51292, and click Continue. When you download fix packages, ensure that you also download the readme file for each fix. Review each readme file for additional installation instructions and information about the fix.
Temporary fix
Comments
APAR Information
APAR number
JR50807
Reported component name
BPM ADVANCED
Reported component ID
5725C9400
Reported release
850
Status
CLOSED PER
PE
NoPE
HIPER
NoHIPER
Special Attention
NoSpecatt
Submitted date
2014-07-17
Closed date
2014-09-24
Last modified date
2014-09-24
APAR is sysrouted FROM one or more of the following:
APAR is sysrouted TO one or more of the following:
Fix information
Fixed component name
BPM ADVANCED
Fixed component ID
5725C9400
Applicable component levels
R850 PSY
UP
[{"Business Unit":{"code":"BU053","label":"Cloud & Data Platform"},"Product":{"code":"SSFTN5","label":"IBM Business Process Manager Advanced"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"8.5","Line of Business":{"code":"LOB45","label":"Automation"}}]
Document Information
Modified date:
16 October 2021