IBM Support

What PTFs must be applied to TWSz 9.2 or IWSZ 9.3 or zWS 9.5 before migration to IZWS / ZWS ( z Workload Scheduler) 9.5 or 10.1?

Question & Answer


Question

Are there specific PTFs which must be applied to earlier releases of z Workload Scheduler before migrating to the latest
releases( ZWS 9.5 and 10.1)? Also are there PTFs for 9.5 or 10.1 that should be applied before migration?

Answer

Changes made April 4, 2023 are marked with a vertical bar "|" in the left margin.
Yes - the Migration chapter (chapter 6) of the  9.5 Planning and Installation Guide begins with this:
Note:To migrate from versions 9.2 and 9.3 to version 9.5  ensure that you have installed the APARs listed in the EQQICNVS sample job
Similarly the Migration chapter for the 10.1 Planning and Installation Guide begins with:
Note: Before migrating ensure that you have installed the required APARs, which are listed in the EQQICNVS sample job.
| (To migrate from 9.2 to 10.1 requires a two-step migration  job - 9.2 to 9.3 or 9.5, then 9.3 or 9.5 to 10.1) 
These comment lines in the 9.5  and 10.1 EQQICNVS job (from SEQQSAMP) give the specific PTFs required:
|  9.5 version of EQQICNVS:
********************* ATTENTION **********************************
** If you are migrating from 920 following PTFs must be       
** correctly installed on 9.2 release:                         
** UI23820, UI23826, and related relevant NLS PTF UI23821,     
** UI23822, UI23823, UI23824 or UI23825)                      
**                                                           
** If you are migrating from 930 following PTFs must be        
** correctly installed on 9.3 release:                        
** UI57072, UI57073 (proxy support SPE)                        
** UI56453, UI56454 (WLM submission SPE)                      
** UI55004, UI55005, UI55006, UI55007, UI51764 (Appl. Deps)   
** UI56453, UI56454 (WLM submssion SPE)                        
** UI51772, UI51762 (Data space SPE)            
| 10.1 version of EQQICNVS:
| ********************* ATTENTION **********************************
| **                                                              
** If you are migrating from 930 following PTFs must be        
** correctly installed on 9.3 release:                          
** UI57072, UI57073 (proxy support SPE)                         
** UI56453, UI56454 (WLM submission SPE)                       
** UI55004, UI55005, UI55006, UI55007, UI51764 (Appl. Deps)     
** UI56453, UI56454 (WLM submssion SPE)                         
** UI51772, UI51762 (Data space SPE)                            
**                                                              
** If you are migrating from 950 following PTFs and Apar        
** must be correctly installed on 9.5 release:                  
** PH30466          (Apar SPE 3)                               
** UI73064, UI73065,                                            
** UI73066, UI73067,                                            
** UI73068, UI73069                                            |
| In addition, for migration from 9.3. all the PTFs listed in the FLASH for PI93525 (PTF UI55004, UI55005) must be applied.
See FLASH technote:  https://www.ibm.com/support/pages/node/729727 
As of October 4, 2020 the PTFs needed are:
     PTF             APAR
  UI56464    PI98960
  UI59216    PI98362 
  UI58124    PH01229
  UI58650    PH02407  
Note that PTF UI56023 is a prerequisite for UI56464, and is the correction for PE PTF  UI52882.
Note also before migrating to the 9.5 release all HIPERs for 9.5 should be applied, including especially the
PTFs for PH22072 -   UI68831, which is superceded by UI68882.
For a list of all the HIPER PTFs for 9.5 see:   https://www.ibm.com/support/pages/node/5694705
| Similarly before migrating to the 10.1 release all HIPERs for 10.1|  should be applied
| For a list of all the HIPER PTFs for 9.5 see:   https://www.ibm.com/support/pages/node/5694705
 Note also that before migratoin to the 10.1 release, all HIPERS for 10.1 should be applied.  For a list
of all the HIPER PTFS for 10.1 see:  https://www.ibm.com/support/pages/node/6619651         
Please ensure that these PTFs are applied.  Also refer to this technote for general issues concerning
migration to a different IZWS release:
migration technote
https://www.ibm.com/support/pages/twsz-migration-new-release-best-practices

[{"Type":"MASTER","Line of Business":{"code":"LOB35","label":"Mainframe SW"},"Business Unit":{"code":"BU058","label":"IBM Infrastructure w\/TPS"},"Product":{"code":"SSWL3F","label":"IBM Z Workload Scheduler"},"ARM Category":[{"code":"a8m0z0000001fw9AAA","label":"ZOS-\u003EIZWS-\u003EMigration to a new release"}],"ARM Case Number":"TS000000000","Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"All Versions"}]

Document Information

Modified date:
04 April 2023

UID

ibm11127883