Maximo Dynamic Job Plans

News


Abstract

Maximo Dynamic Job Plans allows customers using IBM Maximo Asset Management to create job plans where resources are calculated automatically when the job plan is applied to a work order based on the planned unit of work and the total work units.

Customers can select one of four options to determine resource requirements:
• Static (existing IBM Maximo functionality)
• Proportional (resource quantity/duration scales in direct proportion to the the scope of work)
• Level (resource quantity/duration is selected based on predefined thresholds)
• Attribute (resource quantity/duration is calculated based on the asset characteristics as well as scope of work)

Content

Support Information

This package is subject to the terms and conditions displayed upon download.

This download has been prepared and reviewed by IBM. It is offered "AS IS" to existing customers. Support is not provided for this download.

Append a comment to provide feedback and questions.

Maximo Version

7.5.0.0

Requirements

None specified

IBM Products integration works with

IBM Maximo Asset Management

Content type

Technology White Paper

Navcode Reference Number

1TW10MA5I

Industries applied

Cross Industry

Download Content

DJP_V2.0.2.zip

Download License

L-JROZ-76D5RH

Last Content Update: December 4, 2014

[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SSLKT6","label":"IBM Maximo Asset Management"},"Component":"","Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"7.5","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]