Troubleshooting
Problem
Is there a way to default the start date while reporting labor usage?
Resolving The Problem
Setup:
1. Go to the Domains application and create a crossover domain:
2. Attach the crossover domain to the labtrans.refwo field:
3. Run the Database Configuration for the change to take effect.
Test Result:
1. Create a work order.
2. Enter actual start date and time on the main work order tab.
3. Change the status to APPR.
4. Go to actuals tab, labor sub-tab.
5. Click "New Row" button.
6. The crossover domain attached to labtrans.refwo will copy the start date (from STEP 2 above) to the work order's actual start date field (in the ACTUALS tab, LABOR subtab):
Was this topic helpful?
Document Information
Modified date:
17 June 2018
UID
swg21474053