A fix is available
APAR status
Closed as program error.
Error description
The cancel button is inactive during the archive process so it is not possible to stop an archive once started. It should be possible to cancel the archive once it has started. Why is there a cancel button there if it is inactive/greyed out. This is particular problem with very large project archives. It is only possible to stop the archive by going to Task Manager which is not a preferred option.
Local fix
Problem summary
**************************************************************** * USERS AFFECTED: * **************************************************************** * PROBLEM DESCRIPTION: * **************************************************************** * RECOMMENDATION: * **************************************************************** The cancel button is inactive during the archive process so it is not possible to stop an archive once started. It should be possible to cancel the archive once it has started. Why is there a cancel button there if it is inactive/greyed out. This is particular problem with very large project archives. It is only possible to stop the archive by going to Task Manager which is not a preferred option.
Problem conclusion
The code has been changed and the cancel button is now active during the DOORS archive process
Temporary fix
Comments
APAR Information
APAR number
PM24951
Reported component name
TLOGIC DOORS
Reported component ID
5724V61DR
Reported release
930
Status
CLOSED PER
PE
NoPE
HIPER
NoHIPER
Special Attention
NoSpecatt
Submitted date
2010-10-21
Closed date
2012-06-06
Last modified date
2012-06-06
APAR is sysrouted FROM one or more of the following:
APAR is sysrouted TO one or more of the following:
Fix information
Fixed component name
TLOGIC DOORS
Fixed component ID
5724V61DR
Applicable component levels
R930 PSN
UP
[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SSYQBZ","label":"Rational DOORS"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"9.3","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]
Document Information
Modified date:
24 October 2021