Error description
Add ORF support of the following DBD changes for HALDB: 1. Add COMPRTN parameter to a SEGM statement. 2. Remove COMPRTN parameter from a SEGM statement. 3. Change the value for COMPRTN parameter of a SEGM statement. After the above DBD changes, users must perform the IMS Online Change.
Local fix
Problem summary
**************************************************************** * USERS AFFECTED: All users of IBM IMS Database Solution Pack * * V2.1 IMS Online Reorganization Facility who * * use the DBD change feature * **************************************************************** * PROBLEM DESCRIPTION: Add the support of adding, removing and * * changing compression routine for HALDB * **************************************************************** * RECOMMENDATION: * **************************************************************** Add the support of adding, removing and changing compression routine for HALDB.
Problem conclusion
Temporary fix
Comments
======================== = DOCUMENTATION CHANGE = ======================== The IBM IMS Database Solution Pack for z/OS Version 2 Release 1 IMS Online Reorganization Facility User's Guide (SC19-4103-01) ---------------------------------------------------------------- > IMS Online Reorganization Facility overview >> IMS Online Reorganization Facility features and benefits >>> DBD change feature >>>> DBD and DMB replacement DMB cannot be replaced when either of the following conditions is met: - The specified DBD change involves changes to PSBs. - The database is either a PHDAM or PHIDAM database. When either of these conditions is met, a setting of ONLINECHANGE(N) is required. IMS Online Reorganization Facility copies the new DBD to the current DBDLIB and performs an ACBGEN in the staging ACBLIB, but does not modify the IMSACBA and IMSACBB libraries. You must perform an IMS online change after the reorganization. ---------------------------------------------------------------- > IMS Online Reorganization Facility overview >> IMS Online Reorganization Facility features and benefits >>> DBD change feature >>>> Supported DBD changes DBD changes are supported for the following database types: - Full-function databases - HDAM databases - HIDAM databases whose root keys are not compressed - HISAM databases - SHISAM databases - HALDBs - PHDAM databases - PHIDAM databases whose root keys are not compressed Requirements: When you change the DBD of a HALDB, the following conditions must be met: - All partitions must be processed in the IMS Online Reorganization Facility job. - You must specify ONLINECHANGE(N), and perform an IMS online change after the reorganization. Adding or removing a COMPRTN keyword Changing the fourth parameter of the COMPRTN keyword (for full- function databases) Changing COMPRTN parameters (for HALDB databases) Adding a new segment at the end-of-segment-type sequence (for HALDB databases) Adding a new field at the end of the segment or increasing the field length (for HALDB databases) After reorganizing the database using the new definition, IMS Online Reorganization Facility leaves the database offline because a setting of ONLINECHANGE(N) is required. You must manually run the Online Change Copy utility to update the inactive ACBLIB followed by a standard IMS online change, turn off the prohibit authorization flag, and then bring the database back online. ---------------------------------------------------------------- > Using IMS Online Reorganization Facility >> DBD change during reorganization ONLINECHANGE If you specify ONLINECHANGE(N), DMB is not replaced and copy to the IMSACBA and IMSACBB libraries is not performed. After the ACBGEN is performed in the staging ACBLIB, the database remains offline in prohibit authorization status. Perform these steps to complete the DBD change: 1. Use the Online Change Copy utility (DFSUOCU0) and copy the staging ACBLIB to the inactive ACBLIB. Skip this step if you use ACB library member online change. 2. Perform an IMS online change. 3. If the Integrity Checker utility of IMS Library Integrity Utilities is active in your environment, use the LICON utility and re-create the RDE. 4. Turn off the prohibit authorization flag and bring the database back online. ---------------------------------------------------------------- > Using IMS Online Reorganization Facility >> Examples for IMS Online Reorganization Facility >>> Adding or removing a compression routine to a HIDAM database Because adding or removing a compression routine involves change to PSBs, ONLINECHANGE(N) must be specified. After the job ends, you must perform some post-processing tasks. 1.The IMS Online Reorganization Facility job updates the staging ACBLIB with the new database definition, but it does not update the ACBs in online IMS subsystems. The job ends with return code 4, and the HIDAM database remains offline with the prohibit authorization flag turned on. 2. Use the Online Change Copy utility (DFSUOCU0) and copy the staging ACBLIB to the inactive ACBLIB. You can use the OLCUTL procedure to invoke the Online Change Copy utility. Skip this step if you use ACB library member online change. 3. Issue /MODIFY commands or INITIATE OLC commands to complete the IMS online change. 4. If the Integrity Checker utility of IMS Library Integrity Utilities is active in your environment, use the LICON utility and re-create the RDE. 5. Turn off the prohibit authorization flag and restart the database. For a HALDB, you must restart both the HALDB master and each partition. Related topics: See the following topics for IMS functions and utilities: - "Overview of the local online change function" in IMS System Administration - "Overview of the global online change function" in IMS System Administration -"Online Change Copy utility (DFSUOCU0)" in IMS System Utilities -"OLCUTL procedure" in IMS System Utilities -"ACB library member online change" in IMS System Administration ---------------------------------------------------------------- > Troubleshooting >> Messages and codes >>> Messages HRF01182E All partitions required for NEWDBD with HALDB Explanation: The NEWDBD keyword is specified but not all of the HALDB partitions are specified. To change the DBD of a HALDB, all partitions must be processed in the job. System action: Processing terminates. User response: Remove the PARTITION keyword from the command so that all partitions are processed, then resubmit the IMS Online Reorganization Facility job. -------------------------------------------------------------- User Guide Updates: Tech doc will be provided to IBM documentation group to be posted on the Web site.
APAR Information
APAR number
PI48692
Reported component name
IM DB SOLUTION
Reported component ID
5655S7700
Reported release
210
Status
CLOSED UR1
PE
NoPE
HIPER
NoHIPER
Special Attention
YesSpecatt / New Function / Xsystem
Submitted date
2015-09-14
Closed date
2015-10-09
Last modified date
2015-11-03
APAR is sysrouted FROM one or more of the following:
APAR is sysrouted TO one or more of the following:
UI31909
Modules/Macros
HRFODBCM HRFOLEV0 HRFOPST3 HRFOREO0 HRFOREO2 HRFYMSGL HRFYMSGT
SC19410301 |
Fix information
Fixed component name
IM DB SOLUTION
Fixed component ID
5655S7700
Applicable component levels
R210 PSY UI31909
UP15/10/14 P F510
Fix is available
Select the PTF appropriate for your component level. You will be required to sign in. Distribution on physical media is not available in all countries.
[{"Line of Business":{"code":null,"label":null},"Business Unit":{"code":"BU048","label":"IBM Software"},"Product":{"code":"SSCV358","label":"IMS Database Solution Pack"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"2.1.0"}]
Document Information
Modified date:
23 October 2020