Error description
Abend 5C6-00C51045 occurs after CF is deactivated. And queue managers in the QSG receive below messages: CSQE033E +CSQ1 CSQERWIP Recovery phase 1 failed for structure QSG1STR01 connection name QSG1STR1CON1,RC=00000000 reason=00000C06 CSQM056E +CSQ2 CSQMIGQA MQGET failed for queue SYSTEM.QSG.TRANSMIT.QUEUE, MQRC=2345 (MQRC_CF_NOT_AVAILABLE) CSQE007I +CSQ2 CSQESTE EEPLLOSSCONN event received for structure STR01 connection name CSQEQS01CSQ204 CSQE148I +CSQ2 CSQESTE Loss of connectivity processing for structure STR01 has been deferred CSQE007I +CSQ2 CSQESTE EEPLDISCFAILCONNECTION event received for structure STR01 connection name QSG1STR1CON1 CSQE008I +CSQ2 CSQESTE Recovery event from QSC1 received for structure STR01 CSQE015I +CSQ2 CSQESTE Recovery phase 2 not attempted for structure STR01 connection name CSQY291E CSQWDSDM SDUMPX FAILED, RC=00000208,CSQ2,ABN=5C6-00C51045,LOC=CSQELPLM.CSQESTE The problem in this case is that MQ has used an EVENTSEQ# of 0 for the IXLEERSP response to the EeplDiscFailConnection event. The sequence number used is obtained from the STRB for the structure. In this case the STRB PLR sequence number was not updated when phase 1 PLR was requested due to new code added by APAR PH40878 with PTF UI79255 at V920.
Local fix
Problem summary
**************************************************************** * USERS AFFECTED: All users of IBM MQ for z/OS Version 9 * * Release 2 Modification 0 and * * Release 3 Modification 0. * **************************************************************** * PROBLEM DESCRIPTION: Abend 5C6-00C51045 occurs in CSQESTE * * on a queue manager experiencing a CF * * Loss of Connectivity event, if Peer * * Level Recovery (PLR) fails on another * * queue manager and APAR PH40878 (PTF * * UI81566 / UI79255) are applied. * **************************************************************** After applying PH40878, a queue manager experiencing a loss of connectivity to the CF will no longer attempt to perform PLR for another queue manager's failed connection to the CF. However, if a different queue manager attempts PLR for that connection, and is unsuccessful, the failure is broadcast to the affected queue manager. On receiving this broadcast, the queue manager attempts to issue a message indicating that it won't perform Phase 2 of PLR, and this leads to the abend due to reliance on values set in Phase 1 of PLR.
Problem conclusion
CSQESTE is changed to no longer report the overall failure of Phase 1 of PLR on queue managers that are not involved in the PLR operation.
Temporary fix
Comments
APAR Information
APAR number
PH53483
Reported component name
IBM MQ Z/OS V9
Reported component ID
5655MQ900
Reported release
200
Status
CLOSED PER
PE
YesPE
HIPER
NoHIPER
Special Attention
NoSpecatt / Xsystem
Submitted date
2023-03-23
Closed date
2023-06-30
Last modified date
2023-08-01
APAR is sysrouted FROM one or more of the following:
APAR is sysrouted TO one or more of the following:
UI92550 UI92551
Modules/Macros
CSQE197M CSQESEX CSQESTE CSQEWRKT
Fix information
Fixed component name
IBM MQ Z/OS V9
Fixed component ID
5655MQ900
Applicable component levels
Fix is available
Select the PTF appropriate for your component level. You will be required to sign in. Distribution on physical media is not available in all countries.
[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SSYHRD","label":"IBM MQ"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"200","Line of Business":{"code":"LOB45","label":"Automation"}}]
Document Information
Modified date:
01 August 2023