IT36737: NO PROGRESS SEEN IN THE PIE CHART OF RUNNING REPLICATION JOB SUMMARY DURING PROCESSING

Subscribe

You can track all active APARs for this component.

 

APAR status

  • Closed as program error.

Error description

  • In the IBM Spectrum Protect Plus GUI, the job summary
    information for running jobs displays a pie chart to have a
    quick view on the progress of the job.
    
    The running job's summary information is found on the left side
    in the 'Running Jobs' page of the 'Jobs and Operations' GUI
    panel.
    For replications to another vSnap, to Cloud Object Storage or
    to Archive Object Storage, that pie chart is labelled
    'VMs completed: <VMs successfully processed>/
     <Total VMs to Process>'.
    For the above type of jobs, the pie chart does not progress
    during the job and is only briefly populated at job's end right
    before it is moved from the 'Running Jobs' view to the
    'Job History' view.
    That pie chart needs improvement to better display the
    progression of the replication jobs.
    
    IBM Spectrum Protect Plus Versions Affected:
    IBM Spectrum Protect Plus 10.1.x
    
    Initial Impact: Low
    
    Additional Keywords: SPP, SPPLUS, TS005067148
    

Local fix

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * IBM Spectrum Protect Plus levels 10.1.x.                     *
    ****************************************************************
    * PROBLEM DESCRIPTION:                                         *
    * See Error Description.                                       *
    ****************************************************************
    * RECOMMENDATION:                                              *
    * Apply the fixing level when available. This problem is       *
    * projected to be fixed in IBM Spectrum Protect Plus level     *
    * 10.1.8 patch1 and 10.1.9. Note that this is subject to       *
    * change at the discretion of IBM.                             *
    ****************************************************************
    

Problem conclusion

  • IBM Spectrum Protect Plus Jobs and Operations Running and
    History tabs will only show completion status for jobs that
    support it. For running jobs that do not support completion
    status, the Running tab's job entries will not show the pie
    chart and the corresponding "Completed" statistic. For
    historical jobs that did not support completion status, the
    History tab's job entries will not report "Success", "Failed",
    "Skipped" statistics.
    

Temporary fix

Comments

APAR Information

  • APAR number

    IT36737

  • Reported component name

    SP PLUS

  • Reported component ID

    5737SPLUS

  • Reported release

    A17

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2021-04-29

  • Closed date

    2021-05-26

  • Last modified date

    2021-05-26

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

  • Fixed component name

    SP PLUS

  • Fixed component ID

    5737SPLUS

Applicable component levels

[{"Business Unit":{"code":"BU058","label":"IBM Infrastructure w\/TPS"},"Product":{"code":"SSNQFQ","label":"IBM Spectrum Protect Plus"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"A17","Line of Business":{"code":"LOB26","label":"Storage"}}]

Document Information

Modified date:
31 January 2024