IT34974: BACKUP JOB IS NOT FAILING OR CANCELED EVEN IT REACHES THRESHOLD OF REMAINING FREE SPACE

Subscribe

You can track all active APARs for this component.

 

APAR status

  • Closed as program error.

Error description

  • When using IBM Spectrum Protect Plus and doing a backup,
    we check if the threshold of remaining free space is reached.
    If so, we cancel the job and partially fail the backup.
    
    We are checking for 2 conditions
    (Free percentage < freeSpaceErrorPercentage
    && current Free Space < minimumRequiredFreeSpace).
    The default minimumReguiredFreeSpace is 500 (gb).
    The default freeSpaceErrorPercentage is 20 (%).
    
    If the customer has a storage big enough, then the 20%
    of free space is larger than 500GB.
    So the above statement is still false, the job will be
    completed without cancellation and errors.
    The job only fails when the actual free space is below 500 GB.
    

Local fix

  • Set minimumReguiredFreeSpace to 20% of actual vSnap storage
    size.
    

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * IBM Spectrum Protect Plus levels 10.1.6 and 10.1.7.          *
    ****************************************************************
    * PROBLEM DESCRIPTION:                                         *
    * See ERROR DESCRIPTION                                        *
    ****************************************************************
    * RECOMMENDATION:                                              *
    * Apply the fixing level when available. This problem is       *
    * currently projected to be fixed in IBM Spectrum Protect Plus *
    * level 10.1.7 ifix2 and 10.1.8. Note that this is subject to  *
    * change at the discretion of IBM.                             *
    ****************************************************************
    

Problem conclusion

  • Previously during backup, the two conditions free space
    percentage and free space as a value were checked. After the fix
    the logic has changed, so only the remaining space as a
    percentage of the total is checked.
    For IBM Spectrum Protect Plus level 10.1.7 ifix2 only the
    remaining space as a percentage of the total is checked.
    For IBM Spectrum Protect Plus level 10.1.8 in the UI it is
    possible to choose what to use for checking the threshold
    setting. Possibilities are  the remaining space as a percentage
    OR free space as a value OR both.
    

Temporary fix

Comments

APAR Information

  • APAR number

    IT34974

  • Reported component name

    SP PLUS

  • Reported component ID

    5737SPLUS

  • Reported release

    A16

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2020-11-18

  • Closed date

    2021-02-09

  • Last modified date

    2021-04-28

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

  • Fixed component name

    SP PLUS

  • Fixed component ID

    5737SPLUS

Applicable component levels

[{"Business Unit":{"code":"BU058","label":"IBM Infrastructure w\/TPS"},"Product":{"code":"SSNQFQ","label":"IBM Spectrum Protect Plus"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"A16","Line of Business":{"code":"LOB26","label":"Storage"}}]

Document Information

Modified date:
31 January 2024