APAR status
Closed as program error.
Error description
When the restoring calendars to another path task will end with FAILED status, the events failed to be restored will be removed from the source calendar.
Local fix
Problem summary
**************************************************************** * USERS AFFECTED: * * IBM Spectrum Protect Plus level 10.1.5 and 10.1.6 * **************************************************************** * PROBLEM DESCRIPTION: * * See ERROR DESCRIPTION * **************************************************************** * RECOMMENDATION: * * Apply fixing level when available. This problem is fixed in * * IBM Spectrum Protect Plus level 10.1.7 * ****************************************************************
Problem conclusion
When the calendar event is restored to the same account and another path (another calendar) and the restore operation will fail for that event, the original event will be removed in the cleanup process. This problem has been fixed so when the restore operation for the event will fail, the original event will stay untouched.
Temporary fix
Comments
APAR Information
APAR number
IT34538
Reported component name
SP PLUS
Reported component ID
5737SPLUS
Reported release
A16
Status
CLOSED PER
PE
NoPE
HIPER
NoHIPER
Special Attention
NoSpecatt / Xsystem
Submitted date
2020-10-14
Closed date
2020-11-16
Last modified date
2020-11-16
APAR is sysrouted FROM one or more of the following:
APAR is sysrouted TO one or more of the following:
Fix information
Fixed component name
SP PLUS
Fixed component ID
5737SPLUS
Applicable component levels
[{"Business Unit":{"code":"BU058","label":"IBM Infrastructure w\/TPS"},"Product":{"code":"SSNQFQ","label":"IBM Spectrum Protect Plus"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"A16","Line of Business":{"code":"LOB26","label":"Storage"}}]
Document Information