IJ48885: SCHEDULER 7.6.8.2 GRAPHICAL WORK WEEK RESOURCE HOURS NOT UPDATING WHEN LABOUR HOURS ARE 0.

Subscribe to this APAR

By subscribing, you receive periodic emails alerting you to the status of the APAR, along with a link to the fix after it becomes available. You can track this item individually or track all items by product.

Notify me when this APAR changes.

Notify me when an APAR for this component changes.

 

APAR status

  • Closed as program error.

Error description

  • STEPS TO REPRODUCE:
    
    1. Create 2 work orders:
    
    work order A = Add an asset, add a target start date and a
    duration of 4 hours. On the plans tab add a labor entry against
    a craft. Save the record.
    
    
    Duplicate the record, add a target start date and confirm
    there is a duration of 4 hours on the work order tab. Move to
    the plans tab, labour sub-tab, change the regular hour's value
    to 0 hours and save.
    
    
    2. Create a graphical work week record, add a calendar, shift
    and the query to call the 2 work orders created earlier and save
    and move to the Graphical view tab.
    
    
    3. When we look at the duration field both show 4 hours, this
    is incorrect as the 2nd work order was created with 0 hours.
    Seems that the 4 hours is being pulled from the work order tab
    duration field and not the labour sub-tab.
    
    4 Select the 2nd work order created (the record that should have
    the 0 duration for labour) by placing a checkmark next to it,
    now select a labor from the resource section and double-click on
    a date to assign the record. Notice that the Assign Labor box
    shows a 0 value for hours. Press OK and now notice that the day
    that was selected is not updated. But the record shows as
    assigned status.
    
    EXPECTED RESULTS:
    
    
    That the resource hours would have been updated.
    
    Reported in Version:
    
    
    Maximo Asset Management Scheduler 7.6.8.2
    

Local fix

  • N/A
    

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * Scheduler users                                              *
    ****************************************************************
    

Problem conclusion

  • A fix for this APAR will be included in a future release.
    

Temporary fix

Comments

APAR Information

  • APAR number

    IJ48885

  • Reported component name

    MAXIMO SCHEDULE

  • Reported component ID

    5724R46SE

  • Reported release

    768

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2023-10-12

  • Closed date

    2023-10-27

  • Last modified date

    2023-10-27

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

  • Fixed component name

    MAXIMO SCHEDULE

  • Fixed component ID

    5724R46SE

Applicable component levels

[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SS9NUN","label":"Maximo Asset Management Scheduler"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"768","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]

Document Information

Modified date:
27 October 2023