Error description

  • The total Asset cost is incorrect when Services are returned
    
    
    STEPS TO REPRODUCE:
    
    1. System property mxe.workorder.rollupMaintenanceCosts set
    Current Value = 1.
    2. Create a new asset A1 at location BR400.
    3. Change asset status to OPERATING.
    4. Create a new work order WO1 for the new asset A1.
    5. Approve WO1.
    6. Go to actuals tab.
    7. Add a labor record having 4 regular hours, for example ADAMS
    first class driver.
    8. Add a labor record having -4 regular hours, for example ADAMS
    first class driver.
    9. Add a tool record having 4 tool hours, for example FORK.
    10. Add a tool record having -4 tool hours, for example FORK.
    11. Save WO1.
    12. Create a new Purchase Order PO1.
    13. PO Lines TAB -> New Purchase line for SERVICE.
    Line Type: Service, Line cost: 10, Work Order: WO1,
    16. Complete the GL Debit Account and approve PO1.
    17. Go to Receiving and search for PO1.
    18. Go to tab Service Receipts-> button Select Ordered Items
    19. Select the PO line for Service and save the receipt.
    20. Choose Select Services for Return.
    21. Select the PO line for Service and save the return receipt.
    22. Find WO1 in Work Order Tracking.
    23. Verify that WO1 TAB Actuals -> Services with line cost 10
    and one return with Loaded Cost -10
    23. Close WO1 (accept the Open purchase orders exist warning).
    24. Go to Asset A1
    25. Assets Total and YTD Costs equals the absolute sum of all
    actual Line cost on WO1. (175.2 if you have used examples above)
    
    
    
    RESULT:
    
    The Asset Total Cost is 175.20
    
    
    EXPECTED RESULT:
    
    The Assets Total and YTD Costs should be zero
    
    
    REPORTED IN VERSION:
    
    Maximo Asset Management  7.6.1.3
    

Local fix

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * MAXIMO                                                       *
    ****************************************************************
    * PROBLEM DESCRIPTION:                                         *
    * THE TOTAL ASSET COST IS INCORRECT WHEN SERVICES ARE          *
    * RETURNED                                                     *
    ****************************************************************
    

Problem conclusion

  • The fix for this APAR is contained in the following maintenance
    package: release\fix pack for Release 8.7 Product
    

Temporary fix

Comments

APAR Information

  • APAR number

    IJ46276

  • Reported component name

    MAXIMO ASST MGM

  • Reported component ID

    5724R46AM

  • Reported release

    761

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2023-04-03

  • Closed date

    2023-04-18

  • Last modified date

    2023-04-18

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

  • Fixed component name

    MAXIMO ASST MGM

  • Fixed component ID

    5724R46AM

Applicable component levels

[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SSLKT6","label":"Maximo Asset Management"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"761","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]

Document Information

Modified date: