Error description
DESCRIPTION: When using multiple shifts in Graphical Scheduling with PM records and if one Shift duration is not an entire number (example 8:30) then the resource calculation result is 0:01. This is happening when the display mode for Resource load is MONTH, WEEK or DAY. If the display mode is Shift then the load is calculated correctly. STEPS TO REPRODUCE: Prerequisites: 1. Go to Calendars applications 2. Create QTEST calendar with Start Date: 1/1/22 End Date: 1/31/26 3. Create 6 shifts QSA: Monday to Friday 2 PM to 10 PM QSB: Monday to Friday 7 AM to 3 PM QSC: Monday to Friday 7 AM to 3 PM QSD: Monday to Friday 7 AM to 3 PM QSE: Monday to Friday 7 AM to 3 PM QSF: Monday to Friday 7 AM to 3:30 PM 4. Apply shifts to calendar 5. Go to Job Plans application 6. Create 4 Job Plans: JOBPL1 Duration: 4 TASK10: CRAFT1, Quantity 1, Hours 2 TASK20: CRAFT2, Quantity 1, Hours 2 QNINTJP Duration: 16 TASK10: CRAFT1, Quantity 1, Hours 8 TASK20: CRAFT2, Quantity 1, Hours 8 LOA3001 Duration: 15 LOA802 Duration: 5 Labor: PIPE, Quantity 1, Hours 5 7. Go to Preventive Maintenance application 8. Create 4 records PM01 Job Plan: JOBPL1 Last start date: 8/5/22 Earliest Next Due date: 8/8/22 Forecast: generated daily between 8/8/22 and 8/25/22 TESTQ1 Job Plan: QNINTJP Last start date: Earliest Next Due date: 8/4/22 Forecast: generated monthly between 7/27/22 and 12/27/22 LOA1021 Job Plan: LOA3001 Last start date: 3/7/22 Earliest Next Due date: 8/4/22 Forecast: generated monthly between 4/26/22 and 14/21/23 LOA804 Job Plan: LOA802 Last start date: 12/30/16 Earliest Next Due date: 8/4/22 Forecast: generated between 2/18/22 and 2/17/23 Actual steps: 1. Go to Graphical Scheduling application 2. Create new schedule TESTQ1 Calendar: QTEST Shift: QSA,QSB,QSC,QSD,QSE,QSF Start Date: 7/14/22 12:00 AM End Date: 1/10/23 12:00 AM Query: PM, pmnum='PM01,QNINTJP,LOA1021,LOA804' 3.Move to Graphical View RESULT: Resource calculation result is 0:01 REPORTED IN VERSION: Tivoli's process automation engine 7.6.1.2
Local fix
Problem summary
**************************************************************** * USERS AFFECTED: * * Scheduler users * ****************************************************************
Problem conclusion
The fix for this APAR will be included in a future release.
Temporary fix
Comments
APAR Information
APAR number
IJ42427
Reported component name
MAXIMO SCHEDULE
Reported component ID
5724R46SE
Reported release
761
Status
CLOSED PER
PE
NoPE
HIPER
NoHIPER
Special Attention
NoSpecatt / Xsystem
Submitted date
2022-09-12
Closed date
2022-09-30
Last modified date
2022-09-30
APAR is sysrouted FROM one or more of the following:
APAR is sysrouted TO one or more of the following:
Fix information
Fixed component name
MAXIMO SCHEDULE
Fixed component ID
5724R46SE
Applicable component levels
[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SS9NUN","label":"Maximo Asset Management Scheduler"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"761","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]
Document Information
Modified date:
30 September 2022