IJ40332: CRAFT CHECKBOX IN RESOURCES GRAPHICAL VIEW GETS DE-SELECTED UPON MOVING WORK ORDER

Subscribe to this APAR

By subscribing, you receive periodic emails alerting you to the status of the APAR, along with a link to the fix after it becomes available. You can track this item individually or track all items by product.

Notify me when this APAR changes.

Notify me when an APAR for this component changes.

 

APAR status

  • Closed as program error.

Error description

  • When you filter by Ccraft under Resources data
    area in Maximo Graphical Scheduler then you move a work order,
    the checkbox on the craft selected unchecks and another craft?s
    checkbox is checked. The filter on the work order is still on
    the original craft, however, the craft checkbox changes.
    
    
    Steps to replicate:
    
    1.Go to Work Order Tracking and insert a new work order
    
    2.Scroll down to Schedule Start and Schedule Finish date,
    Duration=3
    
    3.Go to Plans tab, insert two tasks
    
    4.Go to Labor sub-tab, insert two lines one for each above task,
    assign a CRAFT to each task, ELECT, CARP,
    
    
    
    5.insert another work order
    
    6.Scroll down to Schedule Start and Schedule Finish date,
    Duration=2
    
    7.Go to Plans tab, insert one task
    
    8.Go to Labor sub-tab, insert a line for task, assign a CRAFT to
    task, CONSTR
    
    
    
    9.Now go to Graphical Scheduling application and create a new
    schedule
    
    10.Enter Calendar=DAY EAGLENA, SHIFT=DAY
    
    11.Create a work order query for the two work orders above
    
    12.Click on the Graphical View tab
    
    13.Scroll down to the Resources Data Area, place a check next to
    first craft
    
    14.Click the toolbar button Filter work orders based on the
    Selected Resources
    
    15.Grab the work order remaining from filter and move it to
    another time or following date
    
    
    
    RESULT: the work order moves and checkmark in the selected Craft
    is removed.
    
    EXPECTED RESULTS:
    The existing checkmark in the selected Craft should not be
    removed
    .
    REPORTED VERSION
    
    
    Tivoli's process automation engine 7.6.1.2
    

Local fix

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * Scheduler users                                              *
    ****************************************************************
    

Problem conclusion

  • The fix for this APAR will be included in a future release.
    

Temporary fix

Comments

APAR Information

  • APAR number

    IJ40332

  • Reported component name

    MAXIMO SCHEDULE

  • Reported component ID

    5724R46SE

  • Reported release

    761

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2022-06-02

  • Closed date

    2023-04-19

  • Last modified date

    2023-04-19

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

  • Fixed component name

    MAXIMO SCHEDULE

  • Fixed component ID

    5724R46SE

Applicable component levels

[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SS9NUN","label":"Maximo Asset Management Scheduler"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"761","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]

Document Information

Modified date:
19 April 2023