IJ40171: GRAPHICAL RESOURCE VIEW IS NOT DISPLAYING DATA

Subscribe to this APAR

By subscribing, you receive periodic emails alerting you to the status of the APAR, along with a link to the fix after it becomes available. You can track this item individually or track all items by product.

Notify me when this APAR changes.

Notify me when an APAR for this component changes.

 

APAR status

  • Closed as program error.

Error description

  • PROBLEM:
    Graphical Resource View is not displaying data
    From research - Shift patterns outside multiples of 7 (and
    including 7) were found to cause the issue of Graphical View now
    displaying data.
    Reproduced in 7.6.1.2 - Graphical Resource View
    
    STEPS TO REPRODUCE:
    
    CALENDAR APPLICATION
    ---
    1. Create a new Calendar
    2. Set the start date to today and the end date to a year from
    now
    3. From the More Actions Menu - click "Define/Apply Shifts"
    4. New Row - Name and set Start Day to MONDAY (as an example)
    5. Set Days in Pattern - set to 5
    6. Click "Define Pattern"
    7. Fill in the chart in the Define Pattern window with Start
    time of 8:00AM and End time of 4:00PM for each day listed >
    click OK
    8. Back in the Define/Apply Shifts window, check the box beside
    the shift you just created and click "Apply Shifts" > In the
    Apply Shifts with Range window, click OK
    9. Back in the Define/Apply Shifts window, click OK
    Note: the shifts should now be listed day-by-day in your
    calendar
    
    LABOR APPLICATION
    ---
    1. Create a New Labor
    2. Scroll Down to the "Personal" section add your Calendar and
    Shift
    3. Enter a First and Last name
    4. Go to the Crafts tab
    5. Create a new row and select a Craft from the Select Value
    list
    
    GRAPHICAL RESOURCE VIEW APPLICATION
    ---
    1. Create a new Graphical Resource List
    2. Select your Calendar from the Select Value list
    3. Select your Shift from the Select Value list
    4. Click on the Graphical View Tab
    Note: no resources are populated
    
    RESULTS:
    When a shift pattern outside a multiple of 7 is used, the
    Graphical View Tab within the Graphical Resource View
    Application comes up blank with no resources listed.  The date
    ribbon is displayed but no data is shown underneath.
    
    EXPECTED RESULTS:
    Expect to see the date ribbon and the labour resources
    displayed.
    
    SYSTEM INFORMATION:
    Maximo 7.6.1.2-IFIX20220216
    

Local fix

  • Adjust shift pattern to fit a multiple of 7 - can leave working
    hours blank on days off.
    

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * Scheduler users                                              *
    ****************************************************************
    

Problem conclusion

  • The fix for this APAR is contained in the following
    maintenancepackage:
    Release 7.6.1.3 of Base Services
    

Temporary fix

Comments

APAR Information

  • APAR number

    IJ40171

  • Reported component name

    MAXIMO SCHEDULE

  • Reported component ID

    5724R46SE

  • Reported release

    768

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2022-05-20

  • Closed date

    2022-05-24

  • Last modified date

    2022-05-24

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

  • Fixed component name

    MAXIMO SCHEDULE

  • Fixed component ID

    5724R46SE

Applicable component levels

[{"Line of Business":{"code":"LOB59","label":"Sustainability Software"},"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SS9NUN","label":"Maximo Asset Management Scheduler"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"768"}]

Document Information

Modified date:
25 May 2022