IJ36494: RESOURCE BAR APPEARS IN RED WHEN THERE IS RESOURCE AVAILABLE

Subscribe to this APAR

By subscribing, you receive periodic emails alerting you to the status of the APAR, along with a link to the fix after it becomes available. You can track this item individually or track all items by product.

Notify me when this APAR changes.

Notify me when an APAR for this component changes.

 

APAR status

  • Closed as program error.

Error description

  • PROBLEM DESCRIPTION:
    Resource bar appears in red when there is resource available
    
    STEPS TO REPRODUCE:
    1. Create a new calendar for 1 month, e.g. 1 Jan 2022 till 31
    Jan 2022 in EAGLENA Organisation
    2. Create a new 7 day shift (SHIFTA) starting on a MONDAY with
    a pattern with Start Time of 7am and end time of 3pm and 8
    hours duration for Monday to Thursday and no work on Friday,
    Saturday or Sunday
    3. Create a new 7 day shift (SHIFTB) starting on a MONDAY with
    a pattern with Start Time of 7am and end time of 3pm and 8
    hours duration for Tuesday to Friday and no work on Saturday,
    Sunday or Monday
    4. Apply both SHIFT A and SHIFT B to the calendar. You should
    see 8 hours on a Monday, 16 hours Tuesday   Thursday , and 8
    hours on Friday
    5. Pick a Labour (in EAGLENA Organisation) with a craft of CARP
    (e.g. FINLEY) and set his calendar to the one created above and
    his shift to SHIFTA
    6. Pick a Labour (in EAGLENA Organisation) with a craft of CARP
    (e.g. MURPHY) and set his calendar to the one created above and
    his shift to SHIFTB
    7. Create a new work order with a target start date in the
    month covered by the calendar, e.g. 3 Jan 2022, with a duration
    of 5 hours and a planned craft of CARP requiring 1 person for
    the 5 hours
    8. Create a new work order with a target start date in the
    month covered by the calendar, e.g. 3 Jan 2022, with a duration
    of 5 hours and a planned craft of CARP requiring 1 person for
    the 5 hours (you can duplicate the previous WO and Approve both
    work orders
    9. Open Graphical Scheduling and create a schedule for the
    calendar above, both SHIFTA and SHIFTB, for start and end dates
    for the month (1-31 Jan 2022) and restrict to dates
    10. For the work order query set up a query that will just
    display the 2 work orders you created
    11. For the Labour query set up a query that will just display
    the 2 labour records we linked the shifts to
    12. Go to the Graphical view
    13. Labour Availability should look like this for a Tuesday:
    14. Drag the first WO from Monday (3 Jan) to the Tuesday (4 Jan)
    15. Drag the second work order to Tuesday (4 Jan). The resource
    bar on the bottom should not go red. It seems the issue is that
    because a the first shift is 8 hours, anything over 8 hours
    changes the colours to red, even though the hours is less than
    available. It seems the calculation to display the hours is
    different from the calculation displaying the colours.
    
    ACTUAL BEHAVIOUR:  resource bar is red in color
    
    EXPECTED BEHAVIOUR:   resource bar should be blue in color
    because there is labor available to do the work
    
    REPORTED IN VERSION:
    IBM Maximo Asset Management 7.6.1.2
    IBM Scheduler 7.6.8
    

Local fix

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * Scheduler users                                              *
    ****************************************************************
    

Problem conclusion

  • The fix for this APAR is contained in the following maintenance
    package: | Release 7.6.1.3 of Base Services
    

Temporary fix

Comments

APAR Information

  • APAR number

    IJ36494

  • Reported component name

    MAXIMO SCHEDULE

  • Reported component ID

    5724R46SE

  • Reported release

    761

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2021-12-10

  • Closed date

    2021-12-15

  • Last modified date

    2021-12-15

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

  • Fixed component name

    MAXIMO SCHEDULE

  • Fixed component ID

    5724R46SE

Applicable component levels

[{"Line of Business":{"code":"LOB59","label":"Sustainability Software"},"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SS9NUN","label":"Maximo Asset Management Scheduler"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"761"}]

Document Information

Modified date:
16 December 2021