IJ35616: GRAPHICAL SCHEDULING - DURATIONS CHANGE WHEN DRAGGING BARS OR ENTERING A NEW START TIME WHEN A TIME ZONE HAS BEEN SPECIFIED

Subscribe to this APAR

By subscribing, you receive periodic emails alerting you to the status of the APAR, along with a link to the fix after it becomes available. You can track this item individually or track all items by product.

Notify me when this APAR changes.

Notify me when an APAR for this component changes.

 

APAR status

  • Closed as program error.

Error description

  • In the Graphical Scheduling (GS) application durations change
    when dragging bars or entering a new start time when a Time
    Zone has been specified.
    When a Time Zone is not specified on Profile - Default
    Information this problem does not occur.
    
    Sometimes changing  a Start time to 11:30am results in it
    changing to 10am by itself.
    
    STEPS TO REPRODUCE:
    1. Go to Profile - Default Information and make sure the Time
    Zone field is blank.   If it is not blank, then blank it out,
    click OK and log out and then log back into Maximo.
    2. Enter a new work order with 2 tasks.   Make the durations of
    all 3 be 2.5 hours.
    3. In Graphical Scheduling create a new schedule with Calendar
    DAY, Shift DAY and a work query to select the new work order.
    4. Save and click on Graphical View.
    5. Click on one of the bars and move it.   It will move and the
    duration will stay at 2:30.   This is the correct behavior.
    6. For a different task change the time on the start date by 1
    hour.   The time will change to what you specified and the
    duration will stay at 2:30.   This is the correct behavior.
    7.  Now go to  Profile - Default Information and enter
    Canada/Central in the Time Zone field.  Log out and then log
    back in.
    8. Open the schedule created above and click on the Graphical
    View tab.
    9. Drag one of the bars to a new time.  For me the duration
    changed to 0:30, for the client it increased.  This is the bug.
    10. For a different task type in a new start time for the start
    date.   Both the time and the duration will change though
    neither one should change.   This is the other part of the bug.
    
    RESULTS:
    They durations and/or start times change when they should stay
    the same.
    
    EXPECTED RESULTS:
    As stated above, the duration should not change.  If typing in
    a new start time, that should not change either from the value
    that has been entered.
    
    REPORTED IN VERSION:
    7612 with the latest IFix.
    

Local fix

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * Scheduler users                                              *
    ****************************************************************
    

Problem conclusion

  • The fix for this APAR is contained in the following maintenance
    package: Release 7.6.1.3 of Base Services
    

Temporary fix

Comments

APAR Information

  • APAR number

    IJ35616

  • Reported component name

    MAXIMO SCHEDULE

  • Reported component ID

    5724R46SE

  • Reported release

    768

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2021-10-18

  • Closed date

    2021-12-07

  • Last modified date

    2021-12-07

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

  • Fixed component name

    MAXIMO SCHEDULE

  • Fixed component ID

    5724R46SE

Applicable component levels

[{"Line of Business":{"code":"LOB59","label":"Sustainability Software"},"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SS9NUN","label":"Maximo Asset Management Scheduler"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"768"}]

Document Information

Modified date:
08 December 2021