  • Closed as program error.

Error description

  • In the Graphical Crew Management (GCM) application drag and
    drop on the Assignment tab does not work.   When you drag an
    orange bar down from the crew row to a labor and save, the bar
    will stay orange and return to the crew row as if it was still
    unassigned.   When you look at the Crews application you see
    the assignment row but you do not see it in GCM.   If you try
    to assign it again in GCM it will say you cannot do it as it
    already exists but you don't see it.
    In the database you may see that the Effective Date and the End
    Date are both at 00:00:00 or you may see the proper times, but
    the assignment bar does not stay with the Labor it was dragged
    to.  It returns to the Crew unassigned section.
    STEPS TO REPRODUCE:
    1. Go to Crafts and make sure at least 2 Crafts have the Crew
    checkbox checked so they can be used with Crews.   If not,
    check it for 2 and Save.
    2. Go to Crew Type and create a new Crew Type.
    3. In the Required Craft section add 2 rows, one for Leader and
    one for Helper.   Use the Crafts that had Crew checked.
    4. Go to Crews and create a new crew using the new Crew Type.
    Do not make any labor assignments for this new Crew.
    5. Go to GCM and create a new Crew List for the new Crew or
    Crew Type.   Give it a Start of next week.  Save.
    6, Go to the Assignments tab and drag one of the orange bars
    down to one of the labor rows and release it.
    7. Save
    RESULTS:
    As discussed above the orange bar does not stay on the chosen
    labor and returns to the Crew section for the unassigned
    assignments.
    EXPECTED RESULTS:
    For the bar to turn green and stay where you left it.
    REPORTED IN VERSION
    7.6.1.2 with IFix
    

Local fix

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * Scheduler users                                              *
    ****************************************************************
    

Problem conclusion

  • The fix for this APAR is contained in the following maintenance
    package: | Release 7.6.1.3 of Base Services
    

Temporary fix

Comments

APAR Information

  • APAR number

    IJ35541

  • Reported component name

    MAXIMO SCHEDULE

  • Reported component ID

    5724R46SE

  • Reported release

    768

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2021-10-12

  • Closed date

    2022-01-05

  • Last modified date

    2022-01-05

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

  • Fixed component name

    MAXIMO SCHEDULE

  • Fixed component ID

    5724R46SE

Applicable component levels

[{"Line of Business":{"code":"LOB59","label":"Sustainability Software"},"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SS9NUN","label":"Maximo Asset Management Scheduler"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"768"}]

Document Information

Modified date:
06 January 2022