Error description

  • After upgrade to Maximo 7.6.1.2 IFIX004, It was noticed that
    work center application is running very slow. Delay was seen in
    load times ? 1 minute, some times taking almost a minute to open
    the applications.
    
    As per development team,
    
    -The new Work Centers UI Layer/Components tap into the
    existing REST APIs.
    -The Maximo Work Centers User Interface (UI) uses the Maximo
    REST API to provide a simplified architecture for building
    Maximo Work Centers based applications. The
    original Maximo UI was built on the server side, whereas the
    Work Centers UI is built on the browser side and uses the Maximo
    REST API to access Maximo Business Objects (MBOs) and Maximo
    data.
    -The initial work center login will take a little extra time
    so the components can load. Once its loaded for the first time
    the components are cached and should load quicker upon the next
    login.
    -Reponses will vary based on connection speeds, server
    configuration, db config, firewalls, network latency, devices
    used, etc.
    
    Steps taken to minimize the load time:
    
    -After the upgrade, multiple database re-orgs and runstats were
    performed which reduced the WORK CENTER loading time from 1
    minute to around 30 seconds.
    Even though performance has improved, expectations were at least
    open within 5 seconds.
    
    -Har files were reviewed and it was identified that 4 REST calls
    that were taking longer than usual which were later investigated
    by development team.
    In order to evaluate the slow running OSLC requests, SQL logging
    was enabled, SQL statements for each long running requests were
    captured and were executed in a database query tool to see how
    long it takes for each one to run.
    
    -Applying vulcanization to Work Centers. Tech note to help
    improve performance with it:
    https://www.ibm.com/support/pages/node/6446949
    Vulcanization did not improve the speed though. It helps with
    the transitioning speed, but when Work Centers starts loading,
    it's still slow.
    
    -Gzip compression was enabled which would help to reduce the
    file size that would improve the speeds too.
    
    -The non-working environment was pointed to the working
    environment's database to see if that improves the performance
    of the non-working environment. Both of the env's databases had
    similar amount of records, so they were comparative databases.
    
    -DB resources increased, indexes added and best practices
    followed :
    https://www.ibm.com/support/pages/best-practices-performance
    
    Actual Result:
    Work center applications are taking ? 1 minute of time to open.
    
    Expected Result:
    Work Center applications should be opening within 5 seconds.
    
    Reported in Version:
    Tivoli's process automation engine 7.6.1.1-IFIX20201221
    

Local fix

  • According to UI L3 team,
    Code fix needed in app-wait.html. Attached() function need to
    comment out appwait.hidden(true)
    
    Also, relationship change for WOSEXPORT was incorrect in prod,
    test, and dev. This change will fix the business analyst work
    center. This is the correct relationship:
    osname=:intobjectname and dataset=:analyticdatasetnum and
    requser=:owner and reqdatetime=(select max(reqdatetime) from
    fileexportreqqueue where osname=:intobjectname and
    dataset=:analyticdatasetnum and requser=:user)
    

Problem summary

  • ****************************************************************
    * PROBLEM DESCRIPTION:                                         *
    * Delay in load times of 10 to 20 seconds for Work Center      *
    * applications.                                                *
    ****************************************************************
    

Problem conclusion

  • A fix for this APAR will be included in a future release.
    

Temporary fix

Comments

APAR Information

  • APAR number

    IJ35025

  • Reported component name

    SYSTEM PERFORMA

  • Reported component ID

    5724R46PF

  • Reported release

    761

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2021-09-16

  • Closed date

    2023-07-05

  • Last modified date

    2023-07-28

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

  • Fixed component name

    SYSTEM PERFORMA

  • Fixed component ID

    5724R46PF

Applicable component levels

[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SSLKT6","label":"Maximo Asset Management"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"761","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]

Document Information

Modified date:
29 July 2023