APAR status
Closed as program error.
Error description
Duration of work orders and tasks changes after entering a value in Graphical Scheduling. STEPS TO REPRODUCE: 1) Create a work order with a few tasks. 2) Create a new scheduler record and add the work order created in step 1. 3) Move to the graphical view tad and enter a duration greater than the length of the shift, e.g. enter a duration of 10 hours. You will see the duration change to a different value. 4) Move the bar in the Gantt view and you will also see the duration randomly change. The duration should not change. EXPECTED RESULTS: That the duration would have remained the same. Reported in Version: Maximo Asset Management Scheduler 7.6.8.0
Local fix
n/a
Problem summary
**************************************************************** * USERS AFFECTED: * * Scheduler users * ****************************************************************
Problem conclusion
The fix for this APAR is contained in the following maintenance package: | Release 7.6.1.3 of Base Services
Temporary fix
Comments
APAR Information
APAR number
IJ34920
Reported component name
MAXIMO SCHEDULE
Reported component ID
5724R46SE
Reported release
768
Status
CLOSED PER
PE
NoPE
HIPER
NoHIPER
Special Attention
NoSpecatt / Xsystem
Submitted date
2021-09-15
Closed date
2021-09-24
Last modified date
2021-09-24
APAR is sysrouted FROM one or more of the following:
APAR is sysrouted TO one or more of the following:
Fix information
Fixed component name
MAXIMO SCHEDULE
Fixed component ID
5724R46SE
Applicable component levels
[{"Line of Business":{"code":"LOB59","label":"Sustainability Software"},"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SS9NUN","label":"Maximo Asset Management Scheduler"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"768"}]
Document Information
Modified date:
25 September 2021