Error description
For a Interruptible=0 work order requiring 10 hours of a Mechanic, in Graphical Scheduling, the load will show 8 hours. This is happening for a DAY/DAY Calendar/Shift combination. The effort is 10 hours so the load should show 10 hours. STEPS TO REPRODUCE: 1. Go to Work Order Tracking 2. Create a work order, duration 10 hours, interruptible=0 3. Add work plan labor of 10 hours of MECH craft 4. Approve the work order 5. Go to Graphical Scheduling 6. Create a work list on DAY/DAY calendar/shift and with a query that includes only the work order created. 7. Move to Graphical View RESULT: In Graphical View the load shows 8.00 hours. EXPEDTED RESULT: In Graphical View the load should show 10.00 hours. REPORTED IN VERSION: IBM Maximo Asset Management 7.6.1.2
Local fix
Set skd.laborHours.spreadAcrossTask property to 1
Problem summary
**************************************************************** * USERS AFFECTED: * * Maximo users * ****************************************************************
Problem conclusion
The fix for this APAR is contained in the following maintenancepackage: Release 7.6.1.3 of Base Services
Temporary fix
Comments
APAR Information
APAR number
IJ32699
Reported component name
MAXIMO SCHEDULE
Reported component ID
5724R46SE
Reported release
761
Status
CLOSED PER
PE
NoPE
HIPER
NoHIPER
Special Attention
NoSpecatt / Xsystem
Submitted date
2021-05-13
Closed date
2021-07-14
Last modified date
2021-07-14
APAR is sysrouted FROM one or more of the following:
APAR is sysrouted TO one or more of the following:
Fix information
Fixed component name
MAXIMO SCHEDULE
Fixed component ID
5724R46SE
Applicable component levels
[{"Line of Business":{"code":"LOB59","label":"Sustainability Software"},"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SS9NUN","label":"Maximo Asset Management Scheduler"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"761"}]
Document Information
Modified date:
15 July 2021