IJ32347: ESTIMATED NEXT DUE DATE (PM.NEXTDATE) IS NOT TAKING ACTIVE DATE RANGE(S) INTO ACCOUNT

Subscribe to this APAR

By subscribing, you receive periodic emails alerting you to the status of the APAR, along with a link to the fix after it becomes available. You can track this item individually or track all items by product.

Notify me when this APAR changes.

Notify me when an APAR for this component changes.

 

APAR status

  • Closed as program error.

Error description

  • When the seasonal dates are defined, the Estimted Next Due Date
    field does not have the same date informed in the Earliest Next
    Due Date field
    
    STEPS TO REPRODUCE:
    
    1) Go to PM Applications
    and create a new PM
    
    2) Under Seasonal Dates
    Active Dates
    Section
    Start Month OCTOBER
    Start Day: 1
    
    End Month: APRIL
    End
    Day: 31
    
    Active Days: all days are marked
    
    3) Under Frequency
    Tab
    Frequency: 1 Months
    Estimted Next Due Date: 04/20/21
    
    Save
    and Active this PM
    
    4) Under More Actions > Generate
    Forecast
    Forecast For (Days): 600
    OK
    
    You will notice that the
    Forecast was generated and it follows the condition of the
    Seasonal Dates.
    Forecase Date:
    10/1/21
    11/1/21
    12/1/21
    1/1/22
    2
    /1/22
    3/1/22
    4/1/22
    10/1/22
    11/1/22
    12/1/22
    
    5) Under More
    Actions > Generate Work Orders
    
    EXPECTED RESULTS: Estimted Next
    Due Date should be 10/1/21 according to the date in the
    Earliest Nest Due Date
    
    RESULTS: Estimated Next Due Date is
    being calculated to be 5/20/21, with May being outside the
    range of the seasonal dates.
    
    REPORTED IN VERSION:
    Version of
    Maximo: 7612
    Application within Maximo: Preventive Mainentance
    

Local fix

  • na
    

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * MAXIMO                                                       *
    ****************************************************************
    * PROBLEM DESCRIPTION:                                         *
    * ESTIMATED NEXT DUE DATE (PM.NEXTDATE) IS NOT TAKING ACTIVE   *
    * DATE RANGE(S) INTO ACCOUNT                                   *
    ****************************************************************
    

Problem conclusion

  • The fix for this APAR is contained in the following maintenance
    package: release\fix pack for Release 7.6.1.3 Product
    

Temporary fix

Comments

APAR Information

  • APAR number

    IJ32347

  • Reported component name

    MAXIMO ASST MGM

  • Reported component ID

    5724R46AM

  • Reported release

    761

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2021-04-27

  • Closed date

    2021-12-22

  • Last modified date

    2021-12-22

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

  • Fixed component name

    MAXIMO ASST MGM

  • Fixed component ID

    5724R46AM

Applicable component levels

[{"Line of Business":{"code":"LOB59","label":"Sustainability Software"},"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SSLKT6","label":"Maximo Asset Management"},"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"761"}]

Document Information

Modified date:
23 December 2021