IBM Support

IJ30716: CREW WORK GROUP DOES NOT CROSSOVER TO ASSIGNMENTS ON WO GENERATED FROM A PM

Subscribe to this APAR

By subscribing, you receive periodic emails alerting you to the status of the APAR, along with a link to the fix after it becomes available. You can track this item individually or track all items by product.

Notify me when this APAR changes.

Notify me when an APAR for this component changes.

 

APAR status

  • Closed as program error.

Error description

  • When you generate a work order from a PM if the Crew Work
    Group is used on the job plan, it crosses over correctly for
    tsks but not for the parent work order.
    If you create a new work order using a task with Crew Work Group
    populated on the planned labor rows, the Crew Work Group crosses
    over correctly to the assignments on the Assignments tab.   It
    does it for both the task and for the parent work order.
    If you create a new job plan with a task with Crew Work Group
    populated on the planned labor rows and then apply that job
    plan to a new work order, the Crew Work Group crosses over
    correctly to the assignments.   It does it for both the task
    and for the
    parent work order.
    If you use that same job plan on a PM and then generate a
    work order, the Crew Work Group crosses over correctly for
    tasks but not for the parent work order.
    STEPS TO REPRODUCE:
    1. Create a new job plan with one task.  Give each a duration
    of any positive number such as 3.
    2. Give each one, the task and the main job plan record, a
    labor.
    3. On both labor rows enter a value for Crew Work Group (this
    is a Person Group, to use it for Crew Work Group you must check
    the Crew Work Group? check-box in the Person Group application).
    4. Save and change status to active.
    5. Go to the Preventive Maintenance application and create a
    new PM using the new job plan.   Give it a location, a
    frequency, an estimated
    next due date and any other required fields.
    6. Save and change status to active.
    7. Generate a work order from this new PM.   You can use
    Frequency Criteria or not.
    RESULTS:
    When you go to the Assignments tab for the work order you will
    see the Crew Work Group populated for the task's assignment but
    not for the parent work order's assignment.
    EXPECTED RESULTS:
    The Crew Work Group should be populated for the task's
    assignment
    and for the parent work order's assignment.   The same way it is
    populated if the job plan was used directly on a new work order
    and for the work order with planned labor not using a job plan.
    REPORTED IN VERSION:
    7.6.1.2 IFix 004
    

Local fix

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * Maximo users                                                 *
    ****************************************************************
    * PROBLEM DESCRIPTION:                                         *
    * Crew Work Group is not populated for the parent Work Order   *
    * assignment when the Work Order is generated from a PM.       *
    ****************************************************************
    

Problem conclusion

  • The fix for this APAR is contained in the following maintenance
    package: release\fix pack for Release 7.6.1.3 Product
    

Temporary fix

Comments

APAR Information

  • APAR number

    IJ30716

  • Reported component name

    MAXIMO ASST MGM

  • Reported component ID

    5724R46AM

  • Reported release

    761

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2021-02-04

  • Closed date

    2021-07-02

  • Last modified date

    2021-07-02

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Fix information

  • Fixed component name

    MAXIMO ASST MGM

  • Fixed component ID

    5724R46AM

Applicable component levels

[{"Type":"MASTER","Line of Business":{"code":"LOB59","label":"Sustainability Software"},"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SSLKT6","label":"IBM Maximo Asset Management"},"Version":"All Versions"}]

Document Information

Modified date:
03 July 2021