Error description

  • PROBLEM:   Optimizer does not allocate labor resource over
    weekends
    
    
    STEPS TO REPRODUCE:
    1. Go to Calendar application and bring up a calendar
    2. Select "Define / Apply Shift" action and define a 5 day
    shift with zero work hours on the weekends
    
    3.  Go to People application and bring up a person record
    Enter the same calendar and shift as step 1 and 2 above
    
    4. Select  Modify Person Availability  action and add
    extra time for the weekends
    
    5. Run Optimization from Graphical Assignment application
    
    
    
    RESULTS:   Optimizer does not assign resources for work orders
    that need to be worked on during weekends
    
    
    EXPECTED RESULTS:  Optimizer should assign resources for work
    orders that need to be worked on during weekends
    
    
    PRODUCT VERSION:
    IBM Maximo for Scheduler 7.6.7.0
    IBM Decision Optimization Center 3.9
    

Local fix

Problem summary

  • ****************************************************************
    * USERS AFFECTED:                                              *
    * Users of the Graphical Assignment application in Scheduler   *
    * 7.6.7.                                                       *
    ****************************************************************
    * PROBLEM DESCRIPTION:                                         *
    * UNABLE TO GET OPTIMIZER TO ALLOCATE LABOR RESOURCE OVER      *
    * WEEKENDS                                                     *
    ****************************************************************
    * RECOMMENDATION:                                              *
    ****************************************************************
    

Problem conclusion

  • A code fix has been made.
    

Temporary fix

Comments

APAR Information

  • APAR number

    IJ16055

  • Reported component name

    MAXIMO SCHEDULE

  • Reported component ID

    5724R46SE

  • Reported release

    767

  • Status

    CLOSED PER

  • PE

    NoPE

  • HIPER

    NoHIPER

  • Special Attention

    NoSpecatt / Xsystem

  • Submitted date

    2019-05-10

  • Closed date

    2019-05-13

  • Last modified date

    2019-05-13

  • APAR is sysrouted FROM one or more of the following:

  • APAR is sysrouted TO one or more of the following:

Modules/Macros

  • MAXIMO
    

Fix information

  • Fixed component name

    MAXIMO SCHEDULE

  • Fixed component ID

    5724R46SE

Applicable component levels

[{"Business Unit":{"code":"BU059","label":"IBM Software w\/o TPS"},"Product":{"code":"SS9NUN","label":"Maximo Asset Management Scheduler"},"Component":"","ARM Category":[],"Platform":[{"code":"PF025","label":"Platform Independent"}],"Version":"767","Edition":"","Line of Business":{"code":"LOB59","label":"Sustainability Software"}}]

Document Information

Modified date:
13 May 2019