Follow these requirements when using water cooling for
the 9125-F2A.
Determining minimum required system flow
and pressure
- Allowable system inlet water temperature range is 6 - 16°C (43
- 61°F), using standard building chilled water (BCW). A special water
system for model 9125-F2A is
typically not required.
- Required flow rate to the cabinet is 3.7 - 79.4 lpm (1 -21 gpm),
depending on inlet water temperature and the number of nodes populated
in the rack. Colder inlet water temperatures require less flow then
warmer water temperatures. Racks that are partially populated with
nodes require less flow than maximum populated racks.
- Minimum water pressure required across the hose ends is 0.34 -
2.32 bar (5 - 33.7 psi), depending on the minimum flow required.
Determining minimum required system flow and pressure
for a normal operating system
- Determine the inlet water temperature. This is the temperature
of the chilled water that is present in the room where the system
is installed.
- Determine the minimum design flow rate for your rack configuration
using tables Required
building chilled water flow, pressure drop and Required building
chilled water flow, pressure drop and outlet temperature (English
units). Under normal operating conditions the flow into the
frame will be double that of the numbers shown in the tables. This
is because both Water Conditioning Units (WCU) in the frame operate
simultaneously.
Note: If there is a possibility that you will add
nodes to a partially populated system at a later date, you should
plan for it during the initial installation.
- Determine the minimum pressure required across the
ends of the hoses to provide the flow rate determined in the step
above. Maximum continuous operating pressure must not exceed 2.32
bars (33.7 psi).
Table 1. Required
building chilled water flow, pressure drop °C (1 of 2)Nodes |
Cooling capacity with two active WCUs |
Required Chilled Water per WCU |
6 |
7 |
8 |
9 |
10 |
2 |
4.9 |
Flow (lpm) |
3.7 |
4 |
4.4 |
4.9 |
5.5 |
Pressure Drop (Bar) |
0.34 |
0.34 |
0.34 |
0.34 |
0.34 |
Outlet temperature °C |
25.1 |
24.4 |
23.8 |
23.2 |
22.7 |
4 |
9.7 |
Flow (lpm) |
8.4 |
9.1 |
9.9 |
10.8 |
11.9 |
Pressure Drop (Bar) |
0.34 |
0.34 |
0.34 |
0.34 |
0.34 |
Outlet temperature °C |
22.7 |
22.4 |
22.2 |
22.0 |
21.8 |
6 |
14.6 |
Flow (lpm) |
13 |
14 |
15.1 |
16.5 |
18.1 |
Pressure Drop (Bar) |
0.34 |
0.34 |
0.34 |
0.34 |
0.34 |
Outlet temperature °C |
22.2 |
22.0 |
21.8 |
21.7 |
21.6 |
8 |
19.5 |
Flow (lpm) |
17.5 |
18.9 |
20.5 |
22.3 |
24.5 |
Pressure Drop (Bar) |
0.34 |
0.34 |
0.34 |
0.34 |
0.34 |
Outlet temperature °C |
21.9 |
21.8 |
21.7 |
21.5 |
21.4 |
10 |
24.4 |
Flow (lpm) |
22.2 |
23.9 |
25.9 |
28.3 |
31.2 |
Pressure Drop (Bar) |
0.34 |
0.34 |
0.34 |
0.34 |
0.39 |
Outlet temperature °C |
21.8 |
21.6 |
21.5 |
21.4 |
21.2 |
12 |
29.2 |
Flow (lpm) |
26.9 |
29 |
31.5 |
34.6 |
38.4 |
Pressure Drop (Bar) |
0.34 |
0.34 |
0.4 |
0.47 |
0.58 |
Outlet temperature °C |
21.6 |
21.5 |
21.3 |
21.1 |
20.9 |
14 |
34.1 |
Flow (lpm) |
31.7 |
34.4 |
37.5 |
41.3 |
46.2 |
Pressure Drop (Bar) |
0.4 |
0.47 |
0.55 |
0.67 |
0.82 |
Outlet temperature °C |
21.4 |
21.2 |
21.1 |
20.8 |
20.6 |
Table 2. Required building chilled
water flow, pressure drop °C (2 of 2)Nodes |
Cooling capacity with two active WCUs |
Required Chilled Water per WCU |
11 |
12 |
13 |
14 |
15 |
16 |
2 |
4.9 |
Flow (lpm) |
6.2 |
7 |
8.1 |
9.6 |
11.5 |
14.4 |
Pressure Drop (Bar) |
0.34 |
0.34 |
0.34 |
0.34 |
0.34 |
0.34 |
Outlet temperature °C |
22.3 |
21.9 |
21.6 |
21.3 |
21.1 |
20.9 |
4 |
9.7 |
Flow (lpm) |
13.2 |
14.8 |
16.9 |
19.7 |
23.6 |
29.5 |
Pressure Drop (Bar) |
0.34 |
0.34 |
0.34 |
0.34 |
0.34 |
0.35 |
Outlet temperature °C |
21.6 |
21.4 |
21.3 |
21.1 |
20.9 |
20.7 |
6 |
14.6 |
Flow (lpm) |
20.1 |
22.6 |
25.9 |
30.3 |
36.8 |
47.8 |
Pressure Drop (Bar) |
0.34 |
0.34 |
0.34 |
0.37 |
0.53 |
0.88 |
Outlet temperature °C |
21.4 |
21.3 |
21.1 |
20.9 |
20.7 |
20.4 |
8 |
19.5 |
Flow (lpm) |
27.3 |
30.8 |
35.5 |
42.2 |
53.1 |
77.8 |
Pressure Drop (Bar) |
0.34 |
0.38 |
0.5 |
0.69 |
1.08 |
2.23 |
Outlet temperature °C |
21.2 |
21.1 |
20.9 |
20.6 |
20.3 |
19.6 |
10 |
24.4 |
Flow (lpm) |
34.9 |
39.8 |
46.5 |
57.1 |
78.5 |
|
Pressure Drop (Bar) |
0.48 |
0.62 |
0.83 |
1.23 |
2.27 |
|
Outlet temperature °C |
21.0 |
20.8 |
20.5 |
20.1 |
19.5 |
|
12 |
29.2 |
Flow (lpm) |
43.3 |
50 |
60.1 |
79 |
|
|
Pressure Drop (Bar) |
0.73 |
0.96 |
1.36 |
2.3 |
|
|
Outlet temperature °C |
20.7 |
20.4 |
20.0 |
19.3 |
|
|
14 |
34.1 |
Flow (lpm) |
52.8 |
62.5 |
79.4 |
|
|
|
Pressure Drop (Bar) |
1.06 |
1.47 |
2.32 |
|
|
|
Outlet temperature °C |
20.3 |
19.8 |
19.2 |
|
|
|
Table 3. Required
building chilled water flow, pressure drop and outlet temperature
(English units) °F (1 of 2)Nodes |
Cooling capacity with two active WCUs |
Required Chilled Water per WCU |
42.8 |
44.6 |
46.4 |
48.2 |
50.0 |
51.8 |
2 |
16.6 |
Flow (gpm) |
1 |
1.1 |
1.2 |
1.3 |
1.5 |
1.6 |
Pressure Drop
(psid) |
5 |
5 |
5 |
5 |
5 |
5 |
Outlet temperature
°F |
77.1 |
75.9 |
74.8 |
73.8 |
72.9 |
72.1 |
4 |
33.3 |
Flow (gpm) |
2.2 |
2.4 |
2.6 |
2.8 |
3.1 |
3.5 |
Pressure Drop
(psid) |
5 |
5 |
5 |
5 |
5 |
5 |
Outlet temperature
°F |
72.8 |
72.3 |
71.9 |
71.6 |
71.2 |
70.9 |
6 |
49.9 |
Flow (gpm) |
3.4 |
3.7 |
4 |
4.4 |
4.8 |
5.3 |
Pressure Drop
(psid) |
5 |
5 |
5 |
5 |
5 |
5 |
Outlet temperature
°F |
71.9 |
71.6 |
71.3 |
71.1 |
70.8 |
70.5 |
8 |
66.6 |
Flow (gpm) |
4.6 |
5 |
5.4 |
5.9 |
6.5 |
7.2 |
Pressure Drop
(psid) |
5 |
5 |
5 |
5 |
5 |
5 |
Outlet temperature
°F |
71.5 |
71.3 |
71.0 |
70.8 |
70.5 |
70.2 |
10 |
83.2 |
Flow (gpm) |
5.9 |
6.3 |
6.8 |
7.5 |
8.2 |
9.2 |
Pressure Drop
(psid) |
5 |
5 |
5 |
5 |
5.6 |
7 |
Outlet temperature
°F |
71.2 |
71.0 |
70.7 |
70.4 |
70.2 |
69.8 |
12 |
99.9 |
Flow (gpm) |
7.1 |
7.7 |
8.3 |
9.1 |
10.1 |
11.4 |
Pressure Drop
(psid) |
5 |
5 |
5.7 |
6.9 |
8.4 |
10.5 |
Outlet temperature
°F |
70.9 |
70.6 |
70.4 |
70.0 |
69.7 |
69.2 |
14 |
116.5 |
Flow (gpm) |
8.4 |
9.1 |
9.9 |
10.9 |
12.2 |
14 |
Pressure Drop
(psid) |
5.8 |
6.8 |
8 |
9.6 |
12 |
15.4 |
Outlet temperature
°F |
70.6 |
70.2 |
69.9 |
69.5 |
69.1 |
68.5 |
Table 4. Required building chilled
water flow, pressure drop and outlet temperature (English units) °F
(2 of 2)Nodes |
Cooling capacity with two active WCUs |
Required Chilled Water per WCU |
53.6 |
55.4 |
57.2 |
59.0 |
60.8 |
2 |
16.6 |
Flow (gpm) |
1.9 |
2.1 |
2.5 |
3 |
3.8 |
Pressure Drop
(psid) |
5 |
5 |
5 |
5 |
5 |
Outlet temperature
°F |
71.5 |
70.9 |
70.4 |
69.9 |
69.6 |
4 |
33.3 |
Flow (gpm) |
3.9 |
4.5 |
5.2 |
6.2 |
7.8 |
Pressure Drop
(psid) |
5 |
5 |
5 |
5 |
5.1 |
Outlet temperature
°F |
70.6 |
70.3 |
70.0 |
69.7 |
69.3 |
6 |
49.9 |
Flow (gpm) |
6 |
6.8 |
8 |
9.7 |
12.6 |
Pressure Drop
(psid) |
5 |
5 |
5.3 |
7.7 |
12.8 |
Outlet temperature
°F |
70.3 |
70.0 |
69.7 |
69.3 |
68.7 |
8 |
66.6 |
Flow (gpm) |
8.1 |
9.4 |
11.2 |
14 |
20.5 |
Pressure Drop
(psid) |
5.5 |
7.2 |
10.1 |
15.6 |
32.4 |
Outlet temperature
°F |
69.9 |
69.6 |
69.1 |
68.5 |
67.3 |
10 |
83.2 |
Flow (gpm) |
10.5 |
12.3 |
15.1 |
20.7 |
|
Pressure Drop
(psid) |
9 |
12.1 |
17.9 |
32.9 |
|
Outlet temperature
°F |
69.4 |
68.9 |
68.2 |
67.0 |
|
12 |
99.9 |
Flow (gpm) |
13.2 |
15.9 |
20.9 |
|
|
Pressure Drop
(psid) |
13.9 |
19.8 |
33.3 |
|
|
Outlet temperature
°F |
68.7 |
68.0 |
66.8 |
|
|
14 |
116.5 |
Flow (gpm) |
16.5 |
21 |
|
|
|
Pressure Drop
(psid) |
21.3 |
33.7 |
|
|
|
Outlet temperature
°F |
67.7 |
66.5 |
|
|
|
Figure 1. Pressure versus flow with a 427 cm (14 ft) hose
– International System of Units (SI units)
Figure 2. Pressure versus flow with a 427 cm (14 ft ) hose
– English units
Note: Curves are with MWU inlet valve in the fully opened position.
The customer pressure-versus-flow behavior of the system will not
match this curve under normal operating conditions because the valve
position adjusts to regulate the flow to maintain a fixed system-side
water temperature.
Principal of operation
- Two pairs of hoses and two WCU's are in parallel at the water
cooling input of the model 9125-F2A. Normally both
of the WCU's operate in parallel to cool the rack, with half
of the water flow circulating through each of the water cooling units.
The control valve in the WCU regulates the flow of water that goes
through it in order to maintain the proper water temperature of the
system-side water in the 9125-F2A.
If the facility water temperature gets cooler, the valve opening
will shrink. If the facility water temperature gets hotter, the valve
will become more open. There must be enough pressure across the ends
of the hoses to force the minimum required amount of water through
the WCUs. This is information is available in Determining minimum required
system flow and pressure.
- The 9125-F2A has
two pairs of hoses and two WCUs. This allows the system to continue
to function even if one of the WCUs should experience some type of
failure. If a WCU fails in a way that does not enable it to cool
the load, the other WCU will pick up the entire rack load. In this
case, the valve in the functioning WCU will open wider to increase
the water flow through it to maintain system temperatures. In addition,
water will likely be shut off to the rear door heat exchanger of the
rack to shed the water cooling load, so the single WCU can cool the
processors in the rack. This causes the heat that is exhausted to
the room to rise. By removing the WCU from the front side, the faulty
WCU can be replaced concurrently, without shutting the system down
to restore the rack water cooling system to its fully redundant state.
It is possible that a faulty WCU could have its input valve stuck
in the full opened position. If this happens, the rack will require
two times the amount of available water flow until the faulty WCU
is repaired. The facility must be capable of providing this additional
flow for this fault case. This is information is available in Determining minimum required
system flow and pressure.
- The system-side water is completely isolated from facility water
by the water-to-water heat exchangers in the WCUs. Heat is transferred
from the system-side water to the facility water by thermal conduction
through the water-to-water heat exchangers. System-side
water is maintained by IBM® service
personnel using special water treated with a corrosion inhibitor.
- Provided that the room dew point is within class 1 specification,
condensation will not form on the system side of the water cooling
system. This is because the system-side water is regulated above the
temperature at which condensation occurs. Condensation will not form
on the facility-side water-cooling system because the components,
including the quick disconnects and hoses, are insulated. Protection
against condensation at the point where the hoses connect to facility
plumbing and condensation protection of the facility side plumbing
itself is a customer responsibility.
Figure 3. Simplified schematic of water cooling system
Calculating building chilled water return temperature
(SI units)
Treturn (°C) = Tsupply (°C)+
14.4 (Q (MWU (kW)/ (MWU BCW Flow (lpm))
Return water
temperature can be calculated under normal operating conditions using
the previous table, Required Building Chilled Water Flow per MWU
(lpm).
Examples in SI unitsTsupply(°C)
= 10. That is, the facilities water is 10 °C.
Frame Heat Load(kw)
= 34.1. T he heat load to water in kilowatts of the system is 34.1
kW.
Frame BCW Flow(gpm) = 44.9. The flow of the facilities
water is 44.9 liters per minute.
Treturn = 10+ 14.4
(34.1/44.9) = 20.9 °C
Calculating building chilled water return temperature
(English units)
Treturn (°F) = Tsupply (F)
+ 2.0 (QMWU (kBTU/hr) / (MWU BCW Flow (gpm))
Return
water temperature can be calculated under normal operating conditions
using the Required Building Chilled Water Flow per MWU (gpm) table.
Examples in English unitsTsupply(°F)
= 50. That is, the facilities water is 50 °F.
Frame Heat Load(kw)
= 116.5 The heat load to water in Kilo British Thermal Units (kBTU)
per hour of the system is 116.5 kBTU per hour.
Frame BCW Flow(gpm)
= 11.9. The flow of the facilities water is 11.9 gallons per minute.
Treturn =
50+2.0 (116.5/11.9) = 69.6 °F
Facility water momentary flow interruption and out
of specification temperature
The system is designed to tolerate
a momentary interruption of facility water flow or temperature increase
that might occur as a result of a failure in the facility water distribution
system.
Momentary interruption of facility water flow
The
system can tolerate complete loss of facilities water flow for 60
seconds. There is a high probability that nodes will be powered off
by thermal protection circuits internal to the 9125-F2A if loss of flow
exceeds this time.
Over-temperature of facility water
The system
can tolerate a 14°C (26°F temperature rise above the maximum facilities
operating temperature at a given flow rate. It should be assumed that
the system will be powered off by the thermal protection circuits
internal to the 9125-F2A for
facility water temperatures greater than this maximum temperature
rise. Continuous operation in an over-temperature condition of 1 -
14°C (2 - 25°F) cannot be sustained, even though the system will run
without powering down. When the maximum allowable facility water temperature
of 16°C (60.8°F) is exceeded, or when the system-side water temperature
cannot be regulated, an error is sent to the customer, and corrective
action is required.
Under-temperature facility water
If facility
water is below the minimum allowable temperature of 4.4 °C (40 °F)
an error will be surfaced to the customer and corrective action will
be required. The only problem that can result from under-temperature
facility water is condensation on the facility side of the system.
The temperature at which condensation might occur is dependant on
the severity of the facility water under-temperature and the air temperature
and humidity in the room.
Facility water quality and fowling
In general
the
9125-F2A requires
standard building chilled water temperatures without any special requirements.
Note: The
facility water flows only through the facility side of the water-to-water
heat exchanges located in the bottom rear of the rack. Therefore,
contaminated facility water cannot damage components within the rack
other than the WCUs.
The quality of the facilities water is
as follows.
- Total hardness must not exceed 200 mg/L as calcium carbonate.
- The pH must be 7 - 9.
- Turbidity must be less than 10 Nephelometric Turbidity Unit (NTU).
- Bacteria must be less than 1000 10 colony forming unit (CFU)/ml.
- Water should be as free of particulate matter as feasible.
Note: Facility water should be tested by qualified personnel
to determine whether it meets these requirements.
Deionized water with benzotriazole
solution installation and maintenance
IBM is responsible for supplying and maintaining
the internal frame secondary loop side water. This protects the system
processor books and distribution plumbing from damage that could result
from the use of contaminated water.
IBM supplies a water solution that is mixed with
benzotriazole (BTA), a corrosion inhibitor, for the internal secondary
cooling loop of the frame when it is installed and when any repairs
are performed that require water to be added.
IBM uses certified suppliers for the water solution
that satisfy all pertinent environmental control requirements.
Deionized water with benzotriazole
disposal
The customer must dispose of the water solution in
accordance with applicable laws and regulations and product characteristics
at the time of disposal.
Internal frame water solutions
IBM will supply the system-side
water.
Water and benzotriazole solution
Benzotriazole
(BTA) is mixed with the deionized (DI) water to a concentration of
1000 parts per million by weight.
Deionized water
The deionized
water used in IBM water cooling
systems conforms to type II, grade A specifications in ASTM D1193-06
entitled, standard specifications for reagent water. Specifications
are as follows:
- Electrical resistivity at 25 °C > 0.5 MΩ•cm
- Total organic carbon < 50 µg/L
- Sodium < 5 µg/L
- Chloride < 5 µg/L
- Total Silica < 3 µg/L
- Total organic carbon < 50 µg/L
- Heterotrophic bacteria count (HBC) less than 10 colony forming
unit (cfu) / 1000 mL as measured per ASTM F1094 or IBM approved equivalent
Benzotriazole
Benzotriazole (BTA) is purchased
from Sigma-Aldrich or an alternative
IBM approved supplier, and is defined as
follows:
- Product Name: Benzotriazole, 99%
- Product Number: B11400
- Brand: Aldrich Chemical
- Substance Name: 1H-Benzotriazole
- Chemical abstracts service number: 95-14-7
- Formula: C6H5N3
- Molecular weight: 119.12
Connection of facility water to the system
Two
pairs of insulated 25.4 mm (1 in.) inside diameter (38.4 mm outside
diameter / 1.51 in.) hoses, which are specified
by IBM, connect facility
water to the system. The hoses are available in 1.83 m (6 ft) and
4.27 m (14 ft) lengths, and can be purchased from IBM or purchased directly
from the hose assembly manufacturer using a part number. The hoses
must be attached to the facility water source, and the system ends
must be properly positioned above the raised floor prior to the server
arriving so that the rack can be rolled into positions, up to the
hoses, without delay.
Installation of IBM system connection hoses in facility
The
following figure shows the four hoses (two supply hoses and two return
hoses) connected to the building water manifolds under the raised
floor with the ends that connect to the system properly positioned
188 mm (7.4 in.) above the floor.
The facility end of the
provided hoses is a cut hose without a fitting. It is the customer's
responsibility to determine the connection technique on this side.
It
is suggested, but not required, that a shutoff valve be provided in
front of the hose assembly as shown. This shutoff valve is not required
for maintenance of the equipment, but can be useful if hose removal
is ever desired by the customer.
The 1.83 m (6 ft) and 4.27
m (14 ft) hose length is the customer's responsibility and depends
on the distance from the facility manifolds to the rack. The facility
end of the hose can be cut to the desired length by the hose installer.
Route the hoses through the floor cutout as shown, being sure
to avoid sharp edges of metal and to leave some slack in the hose.
Cable management is required for signal cables that exit the rear
of the rack and must be considered when routing the hoses. In the
proceeding figure the cable management tray is provided as part of
the facility at the rear of the rack.
IBM hose
assembly ordering information
Four hoses (two supply and
two return) and one hose positioning fixture is required for each
rack that will be installed. The hose positioning fixture is removed
after the hoses are connected to the system.
Ordered hose kits
from IBM arrive with the system.
However, it is recommended that you order the hose kits before the
system, so that they can be attached to the facilities plumbing in
advance. The hose kits must be ordered directly from the hose kit
manufacturer.
Hose assembly ordering information
Two supply
hoses, two return hoses, and one hose positioning fixture are required
for each rack to be installed.
Note: The hose positioning fixture
is removed after the hoses are connected to the system.
In
order for the hose kits to arrive before the system, the hose kits
must be ordered from IBM by
ordering the 9125-F2A Site
Preparation/Install Support Model 9125-F2B. The 9125-F2A Site Preparation/Install
Support Model (9125-F2B) enables the ability to place an order for
the Coolant Supply/Return Hoses (#6876 or #6877) prior to delivery
of the system. This allows the site chilled water plumbing to be
completed ahead of the system arrival, so the hose kits can be attached
to facilities plumbing in advance, reducing overall installation time.
Order either of the following if hoses are required before the systems.
- 9125-F2B 6876 coolant supply and return hoses, 1.83 m (6 ft)
- 9125-F2B 6877 coolant supply and return hoses, 4.27 m (14 ft)
If it is not necessary to receive the hose kits prior to installation,
then you can order the following hose kits:
- Feature code 6876 and part number 45D2215.
- Two 1.83 m (6 ft) hose assembly (black supply) –P/N 45D0907
- Two 1.83 m (6 ft) hose assembly (white return) – P/N 45D0908
- One hose positioning fixture – P/N 45D2245
- Feature code 6877 and part number 45D2214.
- Two 4.27 m (14 ft) hose assembly (black supply) – P/N 45D1952
- Two 4.27 m (14 ft) hose assembly (white return) – P/N 45D1951
- One hose positioning fixture – P/N 45D2245
Figure 4. View of properly positioned facilities hoses
Figure 5. Facility water quick disconnects at rear base of
frame
Figure 6. 9125-F2A water
hook up locations
Hose materials
Only IBM hoses can be used to connect
to the IBM 9125-F2A server. This protects
against leaks and condensation that can result from using insufficient
hose assemblies and incompatible quick disconnect couplings.
The
hose contains the following components:
- Gates terminator hose: 25.4 mm (1 in.) inner diameter (Gates part
number 308504)
- Armacell and Armaflex Hose insulation: Armacell part number APT15838
919-304-3846
- Bentley Harris Expando flame retardant plus protective mesh covering
(Bentley Harris part number BSBHFRP-175)
- Aeroquip System-side quick disconnect couplings (IBM part number 45D0909 or 45D0915)
- Aluminum-bronze elbow and stainless steal clamp
Figure 7. Facilities connection hose
Quick disconnect couplings insulator information
The
quick disconnect coupling insulators shown in the following figure,
are shipped with the system.
Figure 8. Quick disconnect coupling
insulator open and closed
The quick disconnect couplings insulators must be attached
as shown in Quick disconnect couplings without insulator (left)
and with insulator (right) or condensation might occur on the
quick disconnect.
Figure 9. Quick disconnect coupling without
insulator (left) and with insulator (right)
Purging air from facilities-side hoses
It
is recommended that you purge the air from the facilities connection
hoses when the contractor installs the hoses.
The hoses can
contain a maximum of 0.51 liters per meter (0.041 gallons per foot)
of air.
A hose purge operation is not done when the system is
connected to the hoses because it is assumed that purging the hoses
is completed by the hose installation contractor if it is thought
to be necessary in the facility. The suggested procedure to purge
air from the hoses during installation is as follows.
Figure 11. Facilities water quick disconnects (disengaged
with both valves opened)
Figure 12. Facilities water quick disconnects (mated with
one valve opened)
Figure 13. Facilities water quick disconnects (mated with both
valves opened)
- After final connection of the hoses to the facility supply and
return is made, connect the supply quick disconnect coupling to the
return quick disconnect coupling as shown in the preceding figure.
- After the connectors are twisted together, open the valve handle
on one of the two connectors to lock the quick disconnects together.
- Slowly open the valve on the other connector, allowing the air
trapped in the hoses to be moved slowly into the return side of the
facility. Slowly removing the air prevents a large amount of air from
entering the return all at once and allows the air to find its way
to the facility's high point vent.
- After purging is complete, disconnect the quick disconnects from
one another and place them in their proper locations in the positioning
fixture above the raised floor, in preparation for rack installation.
Note: Knowledge of how the water cooling system works is beneficial
to the mechanical engineering firm, mechanical contracting firm, the
plumbing firm, and the customer.