Installation guidelines
Follow these guidelines when installing the IBM c-type SAN device.
- Plan your site configuration and prepare the site before installing the chassis. We recommend that you use the site planning tasks listed in Site planning and maintenance records.
- Ensure that there is adequate space around the switch to allow for servicing the switch and for adequate airflow. Airflow requirements are listed in Product specifications.
- Ensure that the air-conditioning meets the heat dissipation requirements listed in Product specifications.
- Ensure that the rack meets the requirements listed in Rack requirements.
- Ensure that the site power meets the power requirements listed in Product specifications. You can use an uninterruptible power supply (UPS) to protect against power failures.
CAUTION:
Avoid UPS types that use ferroresonant technology. These UPS types can become
unstable with systems such as the IBM c-type SAN Director series, which can have substantial current
draw fluctuations because of fluctuating data traffic patterns.
- Ensure that circuits are sized according to local and national codes. For North America:
- The 3000-W AC power supplies require a 20-A circuit.
- If you are using 200/240 VAC power sources in North America, the circuits must be protected by two-pole circuit breakers.
CAUTION:
To prevent loss of input power, ensure that the total maximum loads on the
circuits supplying power are within the current ratings of the wiring and breakers.
- Record your installation and configuration information as you work. See Site planning and maintenance records.
Use the following screw torques when installing the switch:
- Captive screws: 4 in-lb
- M3 screws: 4 in-lb
- M4 screws: 12 in-lb
- M6 screws: 20 in-lb
- 12-24 screws: 30 in-lb
- 10-20 screws: 22 in-lb