Moving the system to the installation site

Several factors must be considered before moving the system to the installation site.

Prior to moving the system to the installation site, you should:

For more detailed information, see .

If needed, a height reduction feature 7960 might be ordered. This feature allows for the system frame and the expansion frame to be shipped in two pieces and assembled at your location. With this feature, the top section of the system frame (including the power subsystem) is removed. The height of the system frame with the upper section removed is reduced by .35 m (14 in.) to approximately 1.64 m (65 in.). For planning purposes, the weight of the rack top frame and components are shown in the following table.

Table 1. Weight of rack top frame and components
Item Weight1
Rack top frame and crate 210.5 kg (463 lb)
Rack top frame with power (4 bulk power regulators, 4 bulk power distributors, and 2 bulk power assemblies)2 149.5 kg (329 lb)
Bulk power regulator 13.6 kg (30 lb)
Bulk power distributor 6.4 kg (14 lb)
Bulk power assembly 18 kg (40 lb)
Rack top frame without rails 30 kg (66 lb)
Rack top frame with rails 33 kg (73 lb)
Side cover3 22.7 kg (50 lb)
Front acoustic door 17.9 kg (39.4 lb)
Rear acoustic door 17.2 kg (37.9 lb)
Front slimline door 17.2 kg (38 lb)
Rear slimline door 9.1 kg (20 lb)
Note:
  1. Maximum total weight can be up to 255 kg (561 lb)
  2. Can be shipped with up to six bulk power regulators and six bulk power distributors.
  3. Each side cover consists of two panels.

Delivery and subsequent transportation of the equipment

DANGER
Heavy equipment—personal injury or equipment damage might result if mishandled. (D006)

You must prepare your environment to accept the new product based on the installation planning information provided, with assistance from an IBM® Installation Planning Representative (IPR) or IBM authorized service provider. In anticipation of the equipment delivery, prepare the final installation site in advance so that professional movers or riggers can transport the equipment to the final installation site within the computer room. If for some reason, this is not possible at the time of delivery, you must make arrangements to have professional movers or riggers return to finish the transportation at a later date. Only professional movers or riggers should transport the equipment. The IBM authorized service provider can only perform minimal frame repositioning within the computer room, as needed, to perform required service actions. You are also responsible for using professional movers or riggers when you relocate or dispose of equipment.