Performing a rolling upgrade
You can roll out maintenance incrementally in an IBM® Business Process Manager installation that consists of an IBM Process Center and multiple Process Servers, allowing for the continued running of production applications during the upgrade and regression test period.
About this task
Note: A rolling upgrade can be performed only when applying fix packs, refresh packs, or
interim fixes. It cannot be used for migration between major releases.
Restriction: IBM Business Process Manager V8.5.0.0 does not
support context root customization. If you update the context root for the upgraded online Process
Server before upgrading the Process Center, the V8.5.0.0 Process Center will not be able to
communicate with the upgraded Process Server. You must customize the context root only after both
the Process Center and the online Process Server are upgraded.
Procedure
Assuming that you have a development environment, a staging environment, and an offline production server, complete the following steps: